| NYC Department of Buildings | ||
| Electrical Application Details for App #: M392279 | ||
| Premises: 560 1 AVENUE MANHATTAN | BIN: 1085695 Block: 962 Lot: 7501 |
| DOB NOW: Inspections | |||||||||||
| Application Completed and Certified | |||||||||||
| Filed: | 562 FIRST AV | Census Tract: 62 | Health Area: 6000 | |
| 2ND FLOOR | Admin Area: M - MANHATTAN | Inspection Area: N | ||
| NEW YORK, NY 10016 | Community Board: 106 | |||
| Special Place Name: NYU LANGONE MEDICAL CENTER | ||||
| DOB Cross Street(s): EAST 30 STREET, EAST 33 STREET | |||
| Status: C - JOB IS SIGNED OFF 08/17/2018 | |||
| Request Type: A - APPLICATION | eFiled: YES | Permit Issued: 02/15/2017 4:03 PM | |
| Application Entered: 02/15/2017 | Job Start Date: 02/20/2017 | ||
| Last Change: 08/17/2018 | Job End Date: 07/28/2017 | ||
| Appointment Status: | |||
| Last Inspection By: SCHULER, THOMAS On 08/16/2018 | |||
| Field Disp: C - INSPECTION PASSED | |||
| Energize Recommendation: | |||
| Objection Disposition: R - REMOVED | |||
| License #: | 011240 | Licensee Name: | CRAIG GILSTON | |
| Firm: | 000591 | Firm Name: | GILSTON ELEC'L CONTNG LLC | |
| Firm Phone: | 212-410-7800 | Firm Address: | 338 EAST 95TH STREET NEW YORK NY 10128 | |
| Work Started or Filed by Others: NO | ||||||||
| Work Category: R - REHABILITATION | Work To Be Done:
6 - GENERAL WIRING |
Total Fee: $104.25 | ||||||
| Other Work: | ||||||||
| Work Related to a New or Amended Certificate of Occupancy: NO | ||||||||
| This Job Regulated by the NYC Energy Conservation Code: No | ||||||||
| Building Used As: I - Hospital Or Health Facility | |||||||
| Special Cert Approval: | |||||||
| Advisory Board Approval: NOT APPLICABLE | |||||||
| Owner / Occup: | |||||||
| Owner Business Name: | NYU LANGONE MEDICAL CENTE | ||||||
| Authorized Representative: RICHARD COHEN | |||||||
| Relationship To Owner: V.P OF FACILITIES | |||||||
|
|
| Floor | Apt. | Number Of Outlets | No. Of Fixtures |
Motors / Generators | Heaters | Transformers | ||||||
| Fixt | Receptacles | Switch | Num | Total HP KW | Num | Total KW | Num | Total KVA | ||||
| ATT | A/C | |||||||||||
| 002 | 30 | 32 | 22 | 62 | 1 | 1 | ||||||
| Buildings Total | 30 | 32 | 22 | 62 | 1 | |||||||
| Total Units : 147 units | ||||||||||||
| Signs: | Field Connect: | 0 | Field Inspect: | 0 | Tags: | ||
| Meter Request to Utility | #3-Wire | 0 | #4-Wire | 0 | #10-Wire | 0 | |
| Existing Meters | 0 | + New Meters | 0 | - Removed Meters | 0 | = Total Meters | 0 |
| Power Auth Flag: | Objection Flag: | ||
| Power Requested: | Notice: | 1 - FIRST NOTICE 07/18/2018 | |
| Power Issued: | Response: |
| Follow-Up: | K - (CLOSED) | ||
| Contractor's Comments: N/A | |||
|
|