BIS Menu  |  Plumb. Inspections  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: M367961
Premises: 23 ESSEX STREET MANHATTAN BIN: 1003812     Block: 297   Lot: 18
   
Application Completed and Certified

Filed: 23 ESSEX ST Census Tract:   16 Health Area:  7400
BASEMENT AND FIRST FLOOR Admin Area:   M - MANHATTAN Inspection Area:   V
NEW YORK, NY 10002 Community Board:   103
DOB Cross Street(s):   CANAL STREET,    HESTER STREET
Status:   C - JOB IS SIGNED OFF 08/14/2015
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  05/26/2015 10:15 PM
Application Entered:   05/26/2015 Job Start Date:   05/27/2015
Last Change:   08/14/2015 Job End Date:   05/26/2016
Appointment Status:   
Last Inspection By:   CONROY BLAKE       On     07/30/2015      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  E - ISSUE POWER AUTH
Objection Disposition:  

License #: 012398 Licensee Name: WEN BIN CEN
Firm: 004190 Firm Name: R & T ELECTRICAL CORP
Firm Phone: 718-526-6888  Firm Address: 36-03B COLLEGE POINT BLVD BSMNT FLUSHING NY 11354 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
Total Fee:  $156.50
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   K - Store
Store / Other:   RESTAURANT
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: MIKE M WONG
Owner Business Name: 23 ESSEX REALTY CORP
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   Yes
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  1  150AMPS1/0 WIRE
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  1  150AMPS 1/0WIRE
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  1  42 CIRCUIT
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
001    10    10         
Buildings Total 10    10              
Total Units : 36 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 1 #10-Wire 0
Existing Meters 1 + New Meters 1 - Removed Meters 1 = Total Meters 1

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 05/26/2015 Notice:  
Power Issued: 05/26/2015 Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M367961
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 07/30/2015 08/07/2015 CBK C E (40) (0) Y
INSPECTION COMMENTS: NONE




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Plumb. Inspections  |  Electrical Inspection Work Order  |  Back