Electrical Application Details for App #: M361098
Premises: 2 EAST 52 STREET MANHATTAN BIN: 1035479     Block: 1287   Lot: 69
   

DOB NOW: Inspections

Application Completed and Certified

Filed: 2 E 52 ST Census Tract:   102 Health Area:  4800
5TH AVE. Admin Area:   M - MANHATTAN Inspection Area:   L
NEW YORK, NY 10022 Community Board:   105
Special Place Name:   CARTIER'S
DOB Cross Street(s):    5 AVENUE,    MADISON AVENUE
Status:   C - JOB IS SIGNED OFF 11/24/2017
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  11/21/2014 9:30 AM
Application Entered:   11/21/2014 Job Start Date:   11/24/2014
Last Change:   11/24/2017 Job End Date:   04/30/2015
Appointment Status:   
Last Inspection By:   BERGMAN EDUARD       On     11/22/2017      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 010710 Licensee Name: MARC CUSUMANO
Firm: 002039 Firm Name: ARCADIA ELECT'L CO. INC.
Firm Phone: 718-418-0106  Firm Address: 1005 WYCKOFF AVENUE RIDGEWOOD NY 11385 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
2 - TEMPORARY CONSTRUCTION
Total Fee:  $178.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   K - Store
Store / Other:   JEWELRY
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: FRANK NALIBOFF
Owner Business Name: DICKINSON CAMERON
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
001                  10  150     
002                  10  150     
003                  10  112     
004                  10  75     
005                  10  75     
Buildings Total                   562      
Total Units : 562 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  INSTALLING 50 TEMP HEATERS, TO BE DISCONNECTED IN APRIL 2015

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M361098
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 11/22/2017 11/24/2017 EDB C (40) (0) Y
INSPECTION COMMENTS: TEMP. HEATERS REMOVED.