| BUILDING OVERVIEW |
Are Feeders Being Installed? : Yes |
| (If feeders are being installed, provide a wiring diagram and calculations at the time of inspection) |
| Building Overview Work Items |
QUANTITY |
DESCRIPTION |
| SERVICE SWITCHES |
|
| A. Up to 100 AMPS |
0 |
|
| B. 101 Up to 200 AMPS |
0 |
|
| C. 201 Up to 600 AMPS |
0 |
|
| D. 601 Up to 1200 AMPS |
0 |
|
| E. Over 1200 AMPS |
4 |
2-2000,1@3000,1@2500, |
| SER. ENT. & FDR COND (EACH SET) |
|
| A. Up to #2 CONDUCTOR |
15 |
12 @ #2, 3 @ #10 |
| B. Over #2 to 1/0 |
8 |
|
| C. Over 1/0 to 250 MCM |
10 |
8 @ 4/0, 2 @ 2/0 |
| D. Over 250 MCM |
51 |
45 @ 500MCM, 6 @ 350MCM |
| PANELS |
|
| A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs |
0 |
|
| B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs |
0 |
|
| C. 3 Phase Up to 225 AMPS |
0 |
|
| D. 3 Phase Over 225 AMPS |
0 |
|
| ELEVATORS / ESCALATORS / MATERIAL LIFTS |
|
| A. Total No. of Elevators / Escalators / Material Lifts |
0 |
|
| B. Each Additional 10 Floors Or Less |
0 |
|
| BOILER CONTROLS |
0 |
|
| OBJECTION ID |
OBJECTION CODE |
OBJECTION DESCRIPTION & COMMENTS |
STAT |
FIRST |
LATEST |
RESLVD |
| |
| 001 |
(999) |
OTHER (ALL FLOORS) BSMT: NOT INSTALLED PER ADVISORY BOARD DRAWINGSSEE DRAWINGS FOR DETAILS |
RSLV |
11/24/2014 |
11/25/2015 |
02/23/2017 |
| |
| 002 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) T-OUT: ALL ATS SWITCHES ARE 4 WIRE |
RSLV |
11/25/2015 |
11/25/2015 |
12/23/2016 |
| |
| 003 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) SER A: XFMR SEC. SW. -FUSE SIZE |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 004 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) SER B: CON ED STEAM SW-SIZE |
RSLV |
11/25/2015 |
11/25/2015 |
12/23/2016 |
| |
| 005 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) SER B: CON ED STEAM SW- WIRE SIZE |
RSLV |
11/25/2015 |
11/25/2015 |
02/23/2017 |
| |
| 006 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) SER B: CON ED STEAM SW- GROUNDING + BONDING |
RSLV |
11/25/2015 |
11/25/2015 |
12/23/2016 |
| |
| 007 |
(999) |
OTHER (ALL FLOORS) SER B: CON ED STEAM SW-NOT GROUNDED OR BONDED 250.24 |
RSLV |
11/25/2015 |
11/25/2015 |
12/23/2016 |
| |
| 008 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) SER B: S.SW B1 -FUSE SIZE |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 009 |
(999) |
OTHER (ALL FLOORS) SER B: S.SW B1 -LOAD CONDUCTORS OVER FUSED 310.16 |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 010 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS)SER B: 750 KVA-NEUTRAL BONDED IN TRANSFORMER AND SECONDARY SWITCH |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 011 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) SER B: HPP -LGT -MEZZ -OVER FUSED |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 012 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) SER B: FEED FOR BPP-CB UNDERSIZED |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 013 |
(999) |
OTHER (ALL FLOORS)SER B: NEUTRAL BONDED BEYOND SERVICE BPP-CB DISCONNECT 250.24 |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 014 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) ATS RM: CELLAR -WIRES SIZE LOAD SIDE 30 KVA FACP |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 015 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (ALL FLOORS) ATS RM: CELLAR -WIRE SIZE BETWEEN ATS AND 100A SWITCH |
RSLV |
11/25/2015 |
11/25/2015 |
11/28/2016 |
| |
| 016 |
(221) |
NOT INSTALLED PER ADVISORY BOARD DRAWING (CELLAR)SEC. SW. 1600 A (FUSED AT 1200 A) NOT PROPERLY GND 250.30 |
RSLV |
10/05/2016 |
10/05/2016 |
11/28/2016 |
| |
| 017 |
( 5) |
SERVICE GROUNDING CONDUCTOR HAS NOT BEEN INSTALLED PROPERLY (CELLAR)STEAM S. SW. : 1/0 AWG SERV. ENTER CONDUCTOR , # 8 AWG -- GEC250.66 |
RSLV |
10/05/2016 |
10/05/2016 |
11/28/2016 |
| |
| 018 |
( 1) |
SERVICE EQUIPMENT ENCLOSURES ARE NOT BONDED TOGETHER (ROOF) GENERATOR NOT PROPERLY GND 250.30 |
RSLV |
10/05/2016 |
10/05/2016 |
12/23/2016 |
| |
| 019 |
( 56) |
ELECTRICAL MATERIAL USED IS NOT SUITABLE FOR THE PURPOSE INTENDED (ROOF) F/A AND F/P : MISSING NEUTRAL AND DIFFERENT FUSES IN USE110.2,3 215.4 B ,300,3 B |
RSLV |
10/05/2016 |
10/05/2016 |
11/28/2016 |
| |
| 020 |
( 7) |
EMT IS NOT PROPERLY SUPPORTED (TYPE:EMT) (FLOOR: 055) EL. RM. : EMT NOT SECURED FOR GEC 358.30 |
RSLV |
11/28/2016 |
11/28/2016 |
12/23/2016 |
| |
| 021 |
( 22) |
FIXED EQUIPMENT IS NOT PROPERLY GROUNDED (CELLAR)F/A DISC. SW. TO SEC. OF 3W0 KVA : NO EQUIPMENT GND 250.118 |
RSLV |
11/28/2016 |
11/28/2016 |
12/23/2016 |
| |
| 022 |
( 42) |
BUSHINGS ARE MISSING OR LOOSE (CELLAR) F/A DISC. SW. : #2 AWG MISSING BUSHING 300.4 |
RSLV |
11/28/2016 |
11/28/2016 |
12/23/2016 |
| |
| 023 |
( 7) |
EMT IS NOT PROPERLY SUPPORTED (TYPE:EMT) (CELLAR) F/A DISC. SW. TO ATS : EMT NOT SECURED 358.30 |
RSLV |
11/28/2016 |
11/28/2016 |
12/23/2016 |