| BUILDING OVERVIEW |
Are Feeders Being Installed? : Yes |
| (If feeders are being installed, provide a wiring diagram and calculations at the time of inspection) |
| Building Overview Work Items |
QUANTITY |
DESCRIPTION |
| SERVICE SWITCHES |
|
| A. Up to 100 AMPS |
0 |
|
| B. 101 Up to 200 AMPS |
0 |
|
| C. 201 Up to 600 AMPS |
0 |
|
| D. 601 Up to 1200 AMPS |
0 |
|
| E. Over 1200 AMPS |
0 |
|
| SER. ENT. & FDR COND (EACH SET) |
|
| A. Up to #2 CONDUCTOR |
1 |
#3 |
| B. Over #2 to 1/0 |
0 |
|
| C. Over 1/0 to 250 MCM |
0 |
|
| D. Over 250 MCM |
0 |
|
| PANELS |
|
| A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs |
1 |
|
| B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs |
0 |
|
| C. 3 Phase Up to 225 AMPS |
0 |
|
| D. 3 Phase Over 225 AMPS |
0 |
|
| ELEVATORS / ESCALATORS / MATERIAL LIFTS |
|
| A. Total No. of Elevators / Escalators / Material Lifts |
0 |
|
| B. Each Additional 10 Floors Or Less |
0 |
|
| BOILER CONTROLS |
0 |
|
| OBJECTION ID |
OBJECTION CODE |
OBJECTION DESCRIPTION & COMMENTS |
STAT |
FIRST |
LATEST |
RESLVD |
| |
| 001 |
(999) |
OTHER 1FL: REFRIDGE RECE HANGING ON CONDUCTORS,STOVE ALSO |
RSLV |
04/09/2015 |
04/09/2015 |
05/28/2015 |
| |
| 002 |
(999) |
OTHER 1FL: 1 KITCHEN COUNTER CIRCUIT.. 210.52(B)(1) |
RSLV |
04/09/2015 |
04/09/2015 |
05/28/2015 |
| |
| 003 |
(999) |
OTHER 2FL: NO RECE IN HALLWAY.. 210.52(H) |
RSLV |
04/09/2015 |
04/09/2015 |
05/28/2015 |
| |
| 004 |
(999) |
OTHER 1FL: BACK YARD G.F.C.I.. 406.8 |
RSLV |
04/09/2015 |
04/09/2015 |
05/28/2015 |
| |
| 005 |
(128) |
NEUTRAL IS GROUNDED BEYOND LOAD SIDE OF SERVICE SWITCH BASE: IN BASEMENT PANEL FEEDING APT.PANEL,DRYER,ETC |
RSLV |
04/09/2015 |
04/09/2015 |
05/28/2015 |
| |
| 006 |
(999) |
OTHER 1FL: LFNC IN USE.. AM 356.102FL |
RSLV |
04/09/2015 |
04/09/2015 |
05/28/2015 |
| |
| 007 |
(132) |
EQUIPMENT/MATERIAL IS NOT PROPERLY GROUNDED 1FL: REFR.& STOVE REC |
RSLV |
04/09/2015 |
04/09/2015 |
05/28/2015 |