BIS Menu  |  Electrical Inspection Work Order   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: M359019
Premises: 461 WEST 23 STREET MANHATTAN BIN: 1067979     Block: 721   Lot: 7501
   

DOB NOW: Inspections

Application Completed and Certified

Filed: 470 W 24 ST Census Tract:   93 Health Area:  5200
BOILER ROOM Admin Area:   M - MANHATTAN Inspection Area:   P
NEW YORK, NY 10011 Community Board:   104
DOB Cross Street(s):    9 AVENUE,    10 AVENUE
Status:   C - JOB IS SIGNED OFF 03/22/2017
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  09/25/2014 9:37 AM
Application Entered:   09/25/2014 Job Start Date:   09/25/2014
Last Change:   03/22/2017 Job End Date:   03/25/2015
Appointment Status:   
Last Inspection By:   MICHAEL QUERY       On     03/13/2017      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 011991 Licensee Name: ROLAND EDWARDS
Firm: 003719 Firm Name: KRAFT ELECTRIC CORP
Firm Phone: 718-220-2260  Firm Address: 2377 WASHINGTON AVENUE..FL 1 BRONX NY 10458 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
8 - BOILER/BURNER WIRING
Total Fee:  $216.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: CARL REINLIB
Owner Business Name: LODON TERRACE TOWERS
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   Yes
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  1  4 # 4/0 AWG
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  2  100 & 200 AMPS, 30 CIR.
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  2  ST. JOHNSONS

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS          30         
Buildings Total          30           
Total Units : 38 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  WIRING TWO NEW BURNERS.

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M359019
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 03/13/2017 03/15/2017 MQY C (60) (0) Y
INSPECTION COMMENTS: BOILERS CONTROL AND PANEL




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Electrical Inspection Work Order