BUILDING OVERVIEW |
Are Feeders Being Installed? : Yes |
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection) |
Building Overview Work Items |
QUANTITY |
DESCRIPTION |
SERVICE SWITCHES |
|
A. Up to 100 AMPS |
0 |
|
B. 101 Up to 200 AMPS |
0 |
|
C. 201 Up to 600 AMPS |
0 |
|
D. 601 Up to 1200 AMPS |
0 |
|
E. Over 1200 AMPS |
0 |
|
SER. ENT. & FDR COND (EACH SET) |
|
A. Up to #2 CONDUCTOR |
0 |
|
B. Over #2 to 1/0 |
0 |
|
C. Over 1/0 to 250 MCM |
1 |
|
D. Over 250 MCM |
0 |
|
PANELS |
|
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs |
0 |
|
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs |
0 |
|
C. 3 Phase Up to 225 AMPS |
1 |
|
D. 3 Phase Over 225 AMPS |
0 |
|
ELEVATORS / ESCALATORS / MATERIAL LIFTS |
|
A. Total No. of Elevators / Escalators / Material Lifts |
0 |
|
B. Each Additional 10 Floors Or Less |
0 |
|
BOILER CONTROLS |
0 |
|
OBJECTION ID |
OBJECTION CODE |
OBJECTION DESCRIPTION & COMMENTS |
STAT |
FIRST |
LATEST |
RESLVD |
|
001 |
(999) |
OTHER 1ST FL: GND CONDUCTORS NOT PROPERLY TERMINATED AT PNL. 250.8 |
OPEN |
06/04/2014 |
07/23/2014 |
|
|
002 |
(128) |
NEUTRAL IS GROUNDED BEYOND LOAD SIDE OF SERVICE SWITCH 1ST FL: NEUTRAL BONDED AFTER SERVICE SWITCH AT PANEL. 250.24(A5) |
RSLV |
06/04/2014 |
06/04/2014 |
07/23/2014 |
|
003 |
(999) |
OTHER A) T-OUT: BONDING FOR DEVICEAS NOT PROPERLY TERMINATED AT BOXES ASPER 250.8 |
RSLV |
06/04/2014 |
06/04/2014 |
07/23/2014 |
|
004 |
( 14) |
CIRCUIT OVERCURRENT PROTECTION DEVICE IS OF IMPROPER SIZE 1ST FL: A/C IS FUSE OVER MAX RATING AS PER SPEC. 240.3 |
OPEN |
06/04/2014 |
07/23/2014 |
|
|
005 |
(999) |
OTHER B) 1ST FL: ARMORED CABLE FOR A/C NOT PROPERLY TERMINATED AT UNIT320.40 |
OPEN |
06/04/2014 |
07/23/2014 |
|
|
006 |
(145) |
APPLIANCE DISCONNECT NOT PROVIDED/IDENTIFIED. 1ST FL: NO MEANS OF DISCONNECT AT A/C UNIT. 423.30 |
OPEN |
06/04/2014 |
07/23/2014 |
|
|
007 |
(999) |
OTHER 1ST FL: NO G.F.C.I.PROVIDED WITHIN 6FL FROM SINK. 210.8 |
OPEN |
07/23/2014 |
07/23/2014 |
|
|
008 |
(999) |
OTHER A) ROOF: NO OUTLET PROVIDED TO SERVICE A/C UNIT. 210.63 |
OPEN |
07/23/2014 |
07/23/2014 |
|
|
009 |
( 37) |
MOTOR DISCONNECT SWITCH HAS NOT BEEN PROVIDED 1ST FL: CEILING AND AC UNIT |
OPEN |
07/23/2014 |
07/23/2014 |
|
|
010 |
( 24) |
ARMORED CABLES ARE NOT PROPERLY SECURED 1ST FL: CEILING ARMORED CABLE |
OPEN |
07/23/2014 |
07/23/2014 |
|