| BUILDING OVERVIEW |
Are Feeders Being Installed? : Yes |
| (If feeders are being installed, provide a wiring diagram and calculations at the time of inspection) |
| Building Overview Work Items |
QUANTITY |
DESCRIPTION |
| SERVICE SWITCHES |
|
| A. Up to 100 AMPS |
0 |
|
| B. 101 Up to 200 AMPS |
0 |
|
| C. 201 Up to 600 AMPS |
0 |
|
| D. 601 Up to 1200 AMPS |
1 |
|
| E. Over 1200 AMPS |
0 |
|
| SER. ENT. & FDR COND (EACH SET) |
|
| A. Up to #2 CONDUCTOR |
0 |
|
| B. Over #2 to 1/0 |
0 |
|
| C. Over 1/0 to 250 MCM |
0 |
|
| D. Over 250 MCM |
5 |
|
| PANELS |
|
| A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs |
0 |
|
| B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs |
0 |
|
| C. 3 Phase Up to 225 AMPS |
0 |
|
| D. 3 Phase Over 225 AMPS |
0 |
|
| ELEVATORS / ESCALATORS / MATERIAL LIFTS |
|
| A. Total No. of Elevators / Escalators / Material Lifts |
0 |
|
| B. Each Additional 10 Floors Or Less |
0 |
|
| BOILER CONTROLS |
0 |
|
| OBJECTION ID |
OBJECTION CODE |
OBJECTION DESCRIPTION & COMMENTS |
STAT |
FIRST |
LATEST |
RESLVD |
| |
| 001 |
(999) |
OTHER TEMP SVC 3 SETS OF 600 ALUMINUM OVER FUSED AT 1200 AMP... - 310.16 |
RSLV |
07/16/2013 |
07/16/2013 |
07/02/2014 |
| |
| 002 |
(999) |
OTHER TEMP SVC 2ND GND ROD NOT PROVIDED 6'..... - 250.56 |
RSLV |
07/16/2013 |
07/16/2013 |
07/02/2014 |
| |
| 003 |
(999) |
OTHER TEMP SVC 1200 AMP SVC SW NO 3' CLEARANCE.... - 110.26A1 |
RSLV |
07/16/2013 |
07/16/2013 |
07/02/2014 |
| |
| 004 |
(999) |
OTHER TEMP SVC DOORS NOT EQUIPPED WITH PANIC BARS.... - 110.26C2 |
RSLV |
07/16/2013 |
07/16/2013 |
07/02/2014 |
| |
| 005 |
( 4) |
SERVICE IN EXCESS OF 1000KVA HAS NOT BEEN SUBMITTED FOR APPROVAL BASEMENT TEMP SERVICE |
OPEN |
09/11/2014 |
05/21/2015 |
|
| |
| 006 |
(255) |
NO FUSE COORDINATION EXISTS BASEMENT NO FUSES COORDINATIOR |
OPEN |
09/11/2014 |
05/21/2015 |
|
| |
| 007 |
(999) |
OTHER BASEMENT 1200 DISC DOOR NOT OPENING |
OPEN |
09/11/2014 |
05/21/2015 |
|