BIS Menu  |  Electrical Inspection Work Order   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: M340243
Premises: 4 EAST 88 STREET MANHATTAN BIN: 1046924     Block: 1499   Lot: 65
  Printable (PDF) version of this Permit  

DOB NOW: Inspections


Filed: 4 E 88 ST Census Tract:   150.02 Health Area:  3600
APARTMENT 1C Admin Area:   M - MANHATTAN Inspection Area:   J
NEW YORK, NY 10128 Community Board:   108
DOB Cross Street(s):    5 AVENUE,    MADISON AVENUE
Status:   E - ABANDONED 08/22/2025
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  05/09/2013 5:58 PM
Application Entered:   05/09/2013 Job Start Date:   05/10/2013
Last Change:   08/22/2025 Job End Date:   11/10/2013
               COMPLETION FEE WAS BILLED
Appointment Status:   
Last Inspection By:   KAFFETZAKIS, MICHAIL       On     06/18/2013      
Field Disp:   J - JOB IN PROGRESS
Energize Recommendation:  
Objection Disposition:  

License #: 012458 Licensee Name: FERGUS PLUNKETT
Firm: 003307 Firm Name: CAVAN ELECTRIC CORP.
Firm Phone: 718-779-7259  Firm Address: 48-08 70TH STREET WOODSIDE NY 11377 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
Total Fee:  $117.75
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: ASHER WENIG
Owner Business Name: PARK EAST PROPERTY INC.
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  1  1 X 30 CIRCUIT
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
001  1C  20  38  18  42             
Buildings Total 20  38  18  42                
Total Units : 121 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up:
Contractor's Comments:  NEW ELECTRICAL SYSTEM FOR SUPERINTENDENTS APARTMENT

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M340243
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 05/30/2013 06/10/2013 DNM N (20) (0) Y
INSPECTION COMMENTS: *CONTRACTOR NO SHOW*
 
(2) 06/18/2013 06/26/2013 MFF J (5) (0) Y
INSPECTION COMMENTS: NOT READY




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Electrical Inspection Work Order