BIS Menu  |  Electrical Inspection Work Order   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: M333732
Premises: 1379 LEXINGTON AVENUE MANHATTAN BIN: 1048274     Block: 1519   Lot: 52
  Printable (PDF) version of this Permit  

Filed: 1379 LEXINGTON AV Census Tract:   148.02 Health Area:  3600
BASEMENT Admin Area:   M - MANHATTAN Inspection Area:   J
NEW YORK, NY 10128 Community Board:   108
DOB Cross Street(s):   EAST 90 STREET,    EAST 91 STREET
Status:   N - NO ACCESS 06/05/2015
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  11/07/2012 11:28 AM
Application Entered:   11/07/2012 Job Start Date:   11/07/2012
Last Change:   06/05/2015 Job End Date:   01/31/2013
Appointment Status:   
Last Inspection By:   GANITIS, PHILLIP       On     06/01/2015      
Field Disp:   N - NO ACCESS
Energize Recommendation:  
Objection Disposition:  

License #: 012151 Licensee Name: ANTHONY DAIDONE
Firm: 003853 Firm Name: E & M ELEC'L CONTR'G COR
Firm Phone: 718-849-0528  Firm Address: 74-10 69 ROAD MIDDLE VILLAGE NY 11379 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
3 - ELEVATOR/ESCALATOR/MATERIAL LIFT
Total Fee:  $40.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   Z - Commercial/Residential (1  Stores, 20 Apartments)
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: MICHAEL LADISH
Owner Business Name: MATRIX REALTY CO.
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS                     
Buildings Total                       
Total Units : 3 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up:
Contractor's Comments:  INSTALL 1-120VOLT CIRCUIT FOR ELEVATOR MOTOR

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M333732
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 10/29/2013 11/06/2013 TOR N (15) (0) Y
INSPECTION COMMENTS: NO ACCESS TO DEVICE #1W6631
 
(2) 06/03/2014 06/11/2014 IOS N (35) (0) Y
INSPECTION COMMENTS: NO ACCESS TO DEVICE
 
(3) 12/11/2014 12/17/2014 UMS J (10) (0) Y
INSPECTION COMMENTS: APP NOT FILED PROPERLY. LIFT HARD WIRED
 
(4) 06/01/2015 06/05/2015 PHG N (5) (0) Y
INSPECTION COMMENTS: NONE




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.