Electrical Application Details for App #: M313590
Premises: 626 5 AVENUE MANHATTAN BIN: 1083860     Block: 1266   Lot: 1
  Printable (PDF) version of this Permit  

Filed: 45 ROCKEFELLER PLAZA Census Tract:   104 Health Area:  4800
23RD FLOOR Admin Area:   M - MANHATTAN Inspection Area:   L
NEW YORK, NY 10020 Community Board:   105
Special Place Name:   TISHMAN SPEYER
DOB Cross Street(s):   WEST 50 STREET,    WEST 51 STREET
Status:   I - AWAITING INSPECTION REQUEST
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  04/15/2011 7:46 AM
Application Entered:   04/15/2011 Job Start Date:   04/18/2011
Last Change:   03/12/2014 Job End Date:   05/30/2011
Appointment Status:   
Last Inspection By:          On          
Field Disp:   
Energize Recommendation:  
Objection Disposition:  

License #: 011743 Licensee Name: JOSE A LLIGUICHUSHCA
Firm: 001965 Firm Name: NEAD ELECTRIC INC.
Firm Phone: 212-764-2752  Firm Address: 530 WEST 50TH STREET NEW YORK NY 10019 

Other Licensees and Firms:
License # Licensee Name Firm # Firm Name Type
011480 CARDILLO, GREGORY J 001965 NEAD ELECTRIC INC. RESPONSIBLE REP

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
T - TEMPORARY LIGHT & POWER
Total Fee:  $53.50
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   O - Office Bldg
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup:
Owner Business Name: RCPI LANDMARK PROPERTIES
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
023    31      31             
Buildings Total 31      31                
Total Units : 64 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up:
Contractor's Comments:  J-TISHMAN1 - JS FURNISH AND INSTALL TEMPORARY LIGHTING ON THE 23RD FLOOR (WHITE BOX TEMP INSTALLATION). EXISTING SERVICE.

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M313590
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 09/06/2011 09/13/2011 RID Z (0) (0) Y