Electrical Application Details for App #: M292495
Premises: 195 AVENUE A MANHATTAN BIN: 1005999     Block: 440   Lot: 38
   
Application Completed and Certified

Filed: 441 E 12TH Census Tract:   34 Health Area:  6200
BASEMENT Admin Area:   M - MANHATTAN Inspection Area:   T
NEW YORK, NY 10009 Community Board:   103
DOB Cross Street(s):    1 AVENUE,    AVENUE A
Status:   C - JOB IS SIGNED OFF 09/24/2009
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  05/20/2009 8:10 AM
Application Entered:   05/20/2009 Job Start Date:   05/20/2009
Last Change:   09/24/2009 Job End Date:   06/20/2009
Appointment Status:   
Last Inspection By:   BEST, J       On     06/25/2009      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  E - ISSUE POWER AUTH
Objection Disposition:  

License #: 011943 Licensee Name: WARREN M DONDERO
Firm: 003712 Firm Name: BROADWAY ELECTRIC, LLC
Firm Phone: 212-779-4900  Firm Address: 1261 BROADWAY SUITE 609 NEW YORK NY 10001 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
Total Fee:  $150.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   K - Store
Store / Other:   FLORIST
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: DAVID JACOBSON
Owner Business Name: 441 EAST 12TH ST LLC
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   Yes
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  1  200AMP 3 PHASE
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  1  4 X 1/0
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  1  42 CKT 3PHASE/4WIRE
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS                       
Buildings Total                       
Total Units : 1 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 1 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 05/20/2009 Notice:  
Power Issued: 05/20/2009 Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  UPGRADE PANEL AND FEED TO 3 PHASE

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M292495
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 06/25/2009 06/30/2009 JSB C E (45) (0) Y
INSPECTION COMMENTS: NONE