Electrical Application Details for App #: M026426
Premises: 221 WEST 28 STREET MANHATTAN BIN: 1014258     Block: 778   Lot: 28
  Printable (PDF) version of this Permit  

DOB NOW: Inspections


Filed: 221 W 28 ST Census Tract:   95 Health Area:  5200
6FE Admin Area:   M - MANHATTAN Inspection Area:   P
NEW YORK, NY 10001 Community Board:   105
DOB Cross Street(s):    7 AVENUE,    8 AVENUE
Status:   E - ABANDONED 08/22/2025
Request Type:   C - COMPLAINT eFiled:   NO
Application Entered:   09/23/1987 Job Start Date:   12/21/1987
Last Change:   08/22/2025 Job End Date:   12/30/1987
Appointment Status:   
Last Inspection By:   ADMINISTRATION       On     11/05/1999      
Field Disp:   W - ISSUE OBJECTION TO OWNER
Energize Recommendation:  
Objection Disposition:  

License #: 009601 Licensee Name: ARNOLD FINKELSTEIN
Firm: 000160 Firm Name: ARNOLD FINKELSTEIN
Firm Phone: 212-427-9051  Firm Address: 430 EAST 89TH STREET NEW YORK NY 10028 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
Total Fee:  $5.00
Other Work:   REWIRE APT AS NEEDED
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   C - Three Family
Special Cert Approval:  
Advisory Board Approval:  
Owner / Occup:
Owner Business Name: DOUBLE R. ASSOCIATES
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total                         
Total Units : 0 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag: V - OBJECTION(S) EXIST
Power Requested: Notice:  12/07/1987
Power Issued: Response: F - FILED TO REMOVE OBJECTION 12/10/1987

Follow-Up: F - FILED TO REMOVE OBJECTION 12/10/1987
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: M026426
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 09/28/1987 10/13/1987 NC1 W (75) (9)
INSPECTION COMMENTS: SEE BACK SIDE *-GFE.REC.SW.LIGHTS,**-APT BY 1#12,***-BASEMENT OUTDOOR BASEMENT 6TH FLOOR HALL,****-




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Electrical Inspection Work Order