Electrical Application Details for App #: B407785
Premises: 109 SOUTH 5 STREET BROOKLYN BIN: 3063433     Block: 2443   Lot: 34
   

DOB NOW: Inspections

Application Completed and Certified

Filed: 109 S 5TH ST Census Tract:   549 Health Area:  0500
BASEMENT THRU 6TH FLOOR Admin Area:   B - BROOKLYN Inspection Area:   B
BROOKLYN, NY 11249 Community Board:   301
DOB Cross Street(s):   BERRY STREET,    BEDFORD AVENUE
Status:   C - JOB IS SIGNED OFF 09/06/2016
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  02/26/2016 9:20 AM
Application Entered:   02/26/2016 Job Start Date:   02/26/2016
Last Change:   09/06/2016 Job End Date:   07/31/2016
Appointment Status:   
Last Inspection By:   DAMISO COOTE       On     09/01/2016      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 010593 Licensee Name: JOSE A MARENGO
Firm: 002839 Firm Name: ECS ELEC'L CONTG SERV INC
Firm Phone: 718-484-8884  Firm Address: 435 AUSTIN PLACE, SUITE E BRONX NY 10455 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
T - TEMPORARY LIGHT & POWER
Total Fee:  $118.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   O - Office Bldg
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: PETER ANDRESEN
Owner Business Name: MEADOW PARTNERS
Authorized Representative:  PETER ANDRESEN
Relationship To Owner:   PROJECT MANAGER


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS    40                   
001    40                   
002    40                   
003    40                   
004    40                   
005    40                   
006    40                   
Buildings Total 280  42                      
Total Units : 322 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  DEMO AND PROVIDE TEMP LIGHTING

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B407785
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 09/01/2016 09/02/2016 DIT C (50) (0) Y
INSPECTION COMMENTS: JOB PASS