| NYC Department of Buildings | ||
| Electrical Application Details for App #: B387835 | ||
| Premises: 518 PENNSYLVANIA AVENUE BROOKLYN | BIN: 3085055 Block: 3822 Lot: 27 |
| Printable (PDF) version of this Permit | |||||||||||
| DOB NOW: Inspections | |||||||||||
| Filed: | 518 PENNSYLVANIA AV | Census Tract: 1126 | Health Area: 6300 | |
| BASEMENT | Admin Area: B - BROOKLYN | Inspection Area: H | ||
| BROOKLYN, NY 11207 | Community Board: 305 | |||
| DOB Cross Street(s): LIVONIA AVENUE, RIVERDALE AVENUE | |||
| Status: E - ABANDONED 08/22/2025 | |||
| Request Type: A - APPLICATION | eFiled: YES | Permit Issued: 10/24/2014 8:04 PM | |
| Application Entered: 10/24/2014 | Job Start Date: 10/24/2014 | ||
| Last Change: 08/22/2025 | Job End Date: 10/24/2014 | ||
| COMPLETION FEE WAS BILLED | |||
| Appointment Status: | |||
| Last Inspection By: JOHN, CHARLES On 08/15/2015 | |||
| Field Disp: A - OBJCTN ISSD: JOB COMPLETE | |||
| Energize Recommendation: E - ISSUE POWER AUTH | |||
| Objection Disposition: R - REMOVED | |||
| License #: | 011579 | Licensee Name: | KEVIN T KEAVENY | |
| Firm: | 003103 | Firm Name: | KEVIN KEAVENY ELEC CO INC | |
| Firm Phone: | 718-380-0750 | Firm Address: | 158-10 82ND DRIVE JAMAICA NY 11432 | |
| Work Started or Filed by Others: NO | ||||||||
| Work Category: R - REHABILITATION | Work To Be Done:
8 - BOILER/BURNER WIRING |
Total Fee: $64.00 | ||||||
| Other Work: | ||||||||
| Work Related to a New or Amended Certificate of Occupancy: NO | ||||||||
| This Job Regulated by the NYC Energy Conservation Code: No | ||||||||
| Building Used As: Z - Other | |||||||
| Store / Other: C1WALK UP | |||||||
| Special Cert Approval: B - BOILER CONTROLS J-51 CERTIFICATION | |||||||
| Advisory Board Approval: NOT APPLICABLE | |||||||
| Owner / Occup: | MARSHALL MEREDITH | ||||||
| Authorized Representative: | |||||||
| Relationship To Owner: | |||||||
|
|
| Floor | Apt. | Number Of Outlets | No. Of Fixtures |
Motors / Generators | Heaters | Transformers | ||||||
| Fixt | Receptacles | Switch | Num | Total HP KW | Num | Total KW | Num | Total KVA | ||||
| ATT | A/C | |||||||||||
| 001 | BASEM | 1 | 4 | 2 | 3 | |||||||
| Buildings Total | 1 | 4 | 3 | |||||||||
| Total Units : 8 units | ||||||||||||
| Signs: | Field Connect: | 0 | Field Inspect: | 0 | Tags: | ||
| Meter Request to Utility | #3-Wire | 0 | #4-Wire | 0 | #10-Wire | 0 | |
| Existing Meters | 0 | + New Meters | 0 | - Removed Meters | 0 | = Total Meters | 0 |
| Power Auth Flag: | I - ISSUED | Objection Flag: | V - OBJECTION(S) EXIST |
| Power Requested: | 08/25/2015 | Notice: | 1 - FIRST NOTICE 08/25/2015 |
| Power Issued: | 08/25/2015 | Response: |
| Follow-Up: | |||
| Contractor's Comments: WIRE 2 BOILERS | |||
|
|