BIS Menu  |  Applications  |  Elevators  |  Electrical Applications  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: B357820
Premises: 9411 SHORE ROAD BROOKLYN BIN: 3155390     Block: 6111   Lot: 1
   
Application Completed and Certified

Filed: 9411 SHORE RD Census Tract:   54 Health Area:  7810
BASEMENT/BOILER ROOM Admin Area:   B - BROOKLYN Inspection Area:   S
BROOKLYN, NY 11209 Community Board:   310
DOB Cross Street(s):    94 STREET,    RIDGE BOULEVARD
Status:   C - JOB IS SIGNED OFF 04/22/2013
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  12/17/2012 7:48 AM
Application Entered:   12/17/2012 Job Start Date:   12/17/2012
Last Change:   04/22/2013 Job End Date:   03/30/2013
Appointment Status:   
Last Inspection By:   CHARLES COURTNEY       On     04/15/2013      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 011581 Licensee Name: VINCENT LOGOZZO
Firm: 003334 Firm Name: ABILENE ELECTRIC INC
Firm Phone: 718-372-4210  Firm Address: 2402 NEPTUNE AVENUE BROOKLYN NY 11224 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
8 - BOILER/BURNER WIRING
Total Fee:  $52.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:   B - BOILER CONTROLS J-51 CERTIFICATION
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup:
Owner Business Name: TKR PROPERTY SVCS.
Authorized Representative:  JORDAN KUIERS
Relationship To Owner:   PROPERTY MANAGER


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  1  LOW PRESSURE STEAM

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS  BR                   
Buildings Total                     
Total Units : 8 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B357820
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 04/15/2013 04/22/2013 CCH C (45) (0) Y
INSPECTION COMMENTS: N




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Applications  |  Elevators  |  Electrical Applications  |  Electrical Inspection Work Order  |  Back