Electrical Application Details for App #: B349039
Premises: 1171 65 STREET BROOKLYN BIN: 3142008     Block: 5745   Lot: 29
   
Application Completed and Certified

Filed: 1171 65 ST Census Tract:   212 Health Area:  8020
SIDEWALK Admin Area:   B - BROOKLYN Inspection Area:   M
BROOKLYN, NY 11219 Community Board:   310
DOB Cross Street(s):    11 AVENUE,    12 AVENUE
Status:   C - JOB IS SIGNED OFF 10/28/2015
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  04/17/2012 9:31 PM
Application Entered:   04/17/2012 Job Start Date:   04/18/2012
Last Change:   10/28/2015 Job End Date:   04/18/2013
Appointment Status:   
Last Inspection By:   TREJO, JORGE       On     09/22/2015      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 012237 Licensee Name: ROBERT C SAENGER II
Firm: 003997 Firm Name: IDL COMMUNICATIONS AND
Firm Phone: 718-442-9099  Firm Address: 775 4TH AVENUE ELECTRIC INC BROOKLYN NY 11232 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
W - SIDEWALK SHED WIRING & LIGHTING
Total Fee:  $43.50
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   W - School
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: N.Y.C. DEPT. OF EDUCATION
Owner Business Name: SCA
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
GND    12        12             
Buildings Total 12        12                
Total Units : 24 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  SIDEWALK SHED LIGHTING

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B349039
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 09/22/2015 10/01/2015 JTE C (15) (0) Y
INSPECTION COMMENTS: NEW SIDEWALK SHED IN PLACE UNDER APPL #B382874, PREVIOUS SHED UNDER THIS APP HAS BEEN REMOVED