Electrical Application Details for App #: B312436
Premises: 6601 FT HAMILTON PARKWAY BROOKLYN BIN: 3142365     Block: 5757   Lot: 44
   

DOB NOW: Inspections


Filed: 6601 FT HAMILTON PARKWAY Census Tract:   210 Health Area:  8020
BASEMENT Admin Area:   B - BROOKLYN Inspection Area:   M
BROOKLYN, NY 11219 Community Board:   310
DOB Cross Street(s):    66 STREET,    67 STREET
Status:   E - ABANDONED 08/22/2025
Request Type:   P - PICK-UP eFiled:   NO
Application Entered:   01/08/2009 Job Start Date:  
Last Change:   08/22/2025 Job End Date:  
Appointment Status:   
Last Inspection By:   HUGH MCKESSEY       On     01/06/2009      
Field Disp:   W - ISSUE OBJECTION TO OWNER
Energize Recommendation:  
Objection Disposition:  

License #: Licensee Name: UNKNOWN
Firm: Firm Name: UNKNOWN
Firm Phone:   Firm Address:  

Work Started or Filed by Others: NO
Work Category:    Work To Be Done:   Total Fee:  $0.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   K - Store
Store / Other:   GROCERY
Special Cert Approval:  
Advisory Board Approval:  
Owner / Occup: SARANTOS STAMATAKIS
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total                         
Total Units : 0 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag: V - OBJECTION(S) EXIST
Power Requested: Notice: 1 - FIRST NOTICE 01/08/2009
Power Issued: Response:  

Follow-Up: V - OWNER OBJECTION 01/08/2009
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B312436
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 01/06/2009 01/08/2009 HMC W (5) (3)
INSPECTION COMMENTS: N

OBJECTION FOR APPLICATION #: B312436
OBJECTION ID OBJECTION CODE OBJECTION DESCRIPTION & COMMENTS STAT FIRST LATEST RESLVD
 
001 ( 3) APPLICATION FOR CERTIFICATE OF ELECTRICAL INSPECTION NOT ON FILE
BASEMENT AND GROUND FLOORS THROUGHIUT FEEDERS, PANELS, LIGHTS,SWITCHES AND OUTLETS, BRANCH CIRCUITS REFRIGERATOR COMPRESSORS
OPEN 01/06/2009 01/06/2009
 
002 ( 6) FEEDER DIAGRAM DID NOT ACCOMPANY APPLICATION FOR INSPECTION
BASEMENT FEEDER FROM EXISTING 200 AMPS TO FEED GROCERY STORE NEEDLOAD CALCULATIONS
OPEN 01/06/2009 01/06/2009
 
003 ( 56) ELECTRICAL MATERIAL USED IS NOT SUITABLE FOR THE PURPOSE INTENDED
GROUND FLOOR LIGHT FIXTURES OVER FRONT OF STORE UNDER AWNING
OPEN 01/06/2009 01/06/2009