BIS Menu  |  Applications  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: B299967
Premises: 269 ALBANY AVENUE BROOKLYN BIN: 3036665     Block: 1376   Lot: 8
   
Application Completed and Certified

Filed: 269 ALBANY AV Census Tract:   339 Health Area:  4900
BOILER Admin Area:   B - BROOKLYN Inspection Area:   G
BROOKLYN, NY 11213 Community Board:   308
DOB Cross Street(s):   STERLING PLACE,    ST JOHNS PLACE
Status:   C - JOB IS SIGNED OFF 03/12/2008
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  01/18/2008 11:06 AM
Application Entered:   01/18/2008 Job Start Date:   01/18/2008
Last Change:   03/12/2008 Job End Date:   12/15/2009
Appointment Status:   
Last Inspection By:   CAMPBELL, C       On     02/05/2008      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 012003 Licensee Name: JASON R SAMUELS
Firm: 003913 Firm Name: DANIEL'S ELECTRIC INC
Firm Phone: 718-434-3964  Firm Address: 1465A FLATBUSH AVENUE BROOKLYN NY 11210 

Work Started or Filed by Others: YES
Work Category:   R - REHABILITATION Work To Be Done:  
8 - BOILER/BURNER WIRING
Total Fee:  $40.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: SHIMON LIGHTER
Owner Business Name: 269 ALBANY AVE LLC
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total                       
Total Units : 1 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  BOILER WIRING ONLY

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B299967
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 02/05/2008 02/11/2008 CLC C (15) (0) Y
INSPECTION COMMENTS: N




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Applications  |  Electrical Inspection Work Order  |  Back