Electrical Application Details for App #: B267303
Premises: 360 SNEDIKER AVENUE BROOKLYN BIN: 3347581     Block: 3782   Lot: 130
  Printable (PDF) version of this Permit  

DOB NOW: Inspections


Filed: 360 SNEDIKER AV Census Tract:   1134 Health Area:  5900
BASEMENT Admin Area:   B - BROOKLYN Inspection Area:   H
BROOKLYN, NY 11207 Community Board:   305
DOB Cross Street(s):   BLAKE AVENUE,    DUMONT AVENUE
Status:   E - ABANDONED 08/22/2025
Request Type:   P - PICK-UP eFiled:   NO
Application Entered:   06/23/2005 Job Start Date:   06/19/2005
Last Change:   08/22/2025 Job End Date:   08/05/2005
               COMPLETION FEE WAS BILLED
Appointment Status:   
Last Inspection By:   TREJO, JORGE       On     09/24/2014      
Field Disp:   J - JOB IN PROGRESS
Energize Recommendation:  G - NO COMMENT
Objection Disposition:  R - REMOVED

License #: 010903 Licensee Name: JOSE R MARTINEZ
Firm: 002184 Firm Name: C.E. ELECTRICAL CORP
Firm Phone: 888-779-7675  Firm Address: 32-10 57TH STREET STE 2 WOODSIDE NY 11377 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
7 - HVAC WIRING
Total Fee:  $1,121.50
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   I - Hospital Or Health Facility
Special Cert Approval:  
Advisory Board Approval:  
Owner / Occup:
Owner Business Name: BROWNSVILLE CONNUNITY DEV
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  1  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  2  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  2  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  1  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total 51  116    35  51                
Total Units : 253 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 1
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 06/23/2005 Notice:  05/17/2005
Power Issued: 06/23/2005 Response: F - FILED TO REMOVE OBJECTION 06/23/2005

Follow-Up: F - FILED TO REMOVE OBJECTION 06/23/2005
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B267303
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 05/11/2005 05/17/2005 CCH W (15) (1)
INSPECTION COMMENTS: No Inspection Comments For This Application
 
(2) 09/24/2014 09/30/2014 JTE J R G (30) (0) Y
INSPECTION COMMENTS: HEALTH CARE FACILITY UNAWARE OF INSPECTION CONT NO SHOW, NEEDS COMPLE TE INSPECTION, NOT A FINAL