Electrical Application Details for App #: B257758
Premises: 483 5 AVENUE BROOKLYN BIN: 3022924     Block: 1023   Lot: 7
  Printable (PDF) version of this Permit  

Filed: 483 5 AV Census Tract:   139 Health Area:  4600
NONE Admin Area:   B - BROOKLYN Inspection Area:   F
BROOKLYN, NY 11215 Community Board:   306
DOB Cross Street(s):    11 STREET,    12 STREET
Status:   P - OBJECTN PENDING AT CONTRACTOR 12/17/2004
Request Type:   A - APPLICATION eFiled:   NO
Application Entered:   09/02/2004 Job Start Date:   10/01/2004
Last Change:   12/17/2004 Job End Date:   01/15/2005
               COMPLETION FEE WAS BILLED
Appointment Status:   
Last Inspection By:   DOYLEY, DEXTER       On     12/14/2004      
Field Disp:   A - OBJCTN ISSD: JOB COMPLETE
Energize Recommendation:  G - NO COMMENT
Objection Disposition:  

License #: 009514 Licensee Name: RONALD TESTA
Firm: 001416 Firm Name: TESTA ELECTRIC CO., INC
Firm Phone: 718-331-2747  Firm Address: 1435 65TH STREET, 2ND FL BROOKLYN NY 11219 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
Total Fee:  $460.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:  
Owner / Occup: BENNY CARSO
Owner Business Name: 483 5TH AVE CORP
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  1  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  1  
C. Over 1/0 to 250 MCM  6  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  6  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total                       
Total Units : 6 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 7 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: I - ISSUED Objection Flag: V - OBJECTION(S) EXIST
Power Requested: 09/02/2004 Notice: 1 - FIRST NOTICE 12/17/2004
Power Issued: 09/02/2004 Response:  

Follow-Up:
Contractor's Comments:  NEW SERVICE RESERS FOR APT A/C LINE IN EACH APT. PICK UP EXISTINF CIRCUITS

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B257758
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 12/14/2004 12/17/2004 DEX A G (60) (1) Y
INSPECTION COMMENTS: No Inspection Comments For This Application