Electrical Application Details for App #: B201730
Premises: 129 GRAHAM AVENUE BROOKLYN BIN: 3325864     Block: 3070   Lot: 20
   
Application Completed and Certified

Filed: 129 GRAHAM AV Census Tract:   505 Health Area:  1500
080679 1ST FL Admin Area:   B - BROOKLYN Inspection Area:   B
BROOKLYN, NY 11206 Community Board:   301
DOB Cross Street(s):   BOERUM STREET,    JOHNSON AVENUE
Status:   C - JOB IS SIGNED OFF 03/01/2001
Request Type:   A - APPLICATION eFiled:   NO
Application Entered:   05/16/2000 Job Start Date:   05/14/2000
Last Change:   01/16/2001 Job End Date:   06/30/2000
Appointment Status:   
Last Inspection By:   KAGAN, B.       On     01/10/2001      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  E - ISSUE POWER AUTH
Objection Disposition:  

License #: 010759 Licensee Name: YOUNG S CHOE
Firm: 001995 Firm Name: Y.S ELECTRIC
Firm Phone: 866-863-4448  Firm Address: 129-09 26TH AVENUE, #103 FLUSHING NY 11354 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
9 - OTHER
Total Fee:  $88.25
Other Work:   UPGRADING EXISTING 2 WIRE METER TO 3 WIRE
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   K - Store
Store / Other:   1 HR PHOTO SHOP
Special Cert Approval:  
Advisory Board Approval:  
Owner / Occup: YOUNG BAE
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  1  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  2  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  1  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total             
Total Units : 19 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 1 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 05/16/2000 Notice:  
Power Issued: 05/16/2000 Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  

 
Inspection Details
 

INSPECTION FOR APPLICATION #: B201730
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 01/10/2001 01/16/2001 BK1 C E (65) (0)
INSPECTION COMMENTS: No Inspection Comments For This Application