BIS Menu  |  Property Profile  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: A303747
Premises: 23-37 31 DRIVE QUEENS BIN: 4538170     Block: 568   Lot: 206
   
Application Completed and Certified

Filed: 23-37 31 DR Census Tract:   75
ENTIRE BUILDING Admin Area:   A - QUEENS Inspection Area:   A
QUEENS, NY 11106 Community Board:   401
Related Job Number:    420182028
DOB Cross Street(s):    23 STREET,    CRESCENT STREET
Status:   C - JOB IS SIGNED OFF 07/19/2013
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  07/23/2012 10:37 PM
Application Entered:   07/23/2012 Job Start Date:   07/24/2012
Last Change:   07/19/2013 Job End Date:   12/31/2013
Appointment Status:   
Last Inspection By:   BOTSCH, E       On     05/20/2013      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  E - ISSUE POWER AUTH
Objection Disposition:  

License #: 012175 Licensee Name: HARRY G DOUNIS
Firm: 004043 Firm Name: TEMPEST ELEC'L CONTRG, IN
Firm Phone: 718-357-5210  Firm Address: 152-53 10TH AVENUE, SUITE 215D WHITESTONE NY 11357 

Work Started or Filed by Others: NO
Work Category:   N - NEW BUILDING Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
8 - BOILER/BURNER WIRING
Total Fee:  $264.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   YES
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: JOHN ARGYROS
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   Yes
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  6  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  1  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  5  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
CEL    10                 
LOB    10             
002    20             
003  16             
003  16             
004  16             
004  16             
Buildings Total 38  104  12  41  39                
Total Units : 234 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 6 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 6 - Removed Meters 0 = Total Meters 6

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 07/23/2012 Notice:  
Power Issued: 07/23/2012 Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  NEW BUILDING

 
Inspection Details
 

INSPECTION FOR APPLICATION #: A303747
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 05/20/2013 06/04/2013 EBT C E (30) (0) Y
INSPECTION COMMENTS: CERTIFICATE




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Property Profile  |  Electrical Inspection Work Order  |  Back