BIS Menu  |  Plumb. Inspections  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: A285019
Premises: 54-40 LITTLE NECK PARKWAY QUEENS BIN: 4171524     Block: 8256   Lot: 108
  Printable (PDF) version of this Permit  

DOB NOW: Inspections


Filed: 54-40 LITTLE NECK PKWY Census Tract:   1507.02 Health Area:  2150
54-40 LITTLE NECK PKWY Admin Area:   A - QUEENS Inspection Area:   F
QUEENS, NY 11362 Community Board:   411
Special Place Name:   NASSUA BLVD
DOB Cross Street(s):   LEEDS ROAD,    NASSAU BOULEVARD
Status:   E - ABANDONED 08/22/2025
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  03/31/2010 1:02 PM
Application Entered:   03/31/2010 Job Start Date:   03/31/2010
Last Change:   08/22/2025 Job End Date:   04/29/2010
Appointment Status:   
Last Inspection By:          On          
Field Disp:   
Energize Recommendation:  
Objection Disposition:  

License #: 011697 Licensee Name: MICHAEL MURPHY
Firm: 002280 Firm Name: ASSOCIATED ELEC CONT OF N
Firm Phone: 718-882-9520  Firm Address: 27 EAST 233RD STREET NY INC. BRONX NY 10470 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
Total Fee:  $40.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: FREDRICK M WILLIAMS
Owner Business Name: CLEAR WIRELESS LLC
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
ROF                   
Buildings Total                       
Total Units : 4 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up:
Contractor's Comments:  CONNECT COMMUNICATIONS CABINET TO EXISTING PANEL. 1 60AMP CIRCUIT.

 
 

*NO INSPECTION RECORDS FOUND FOR ELECTRICAL APPLICATION NUMBER A285019
INSPECTION FOR APPLICATION #: A285019
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE