Electrical Application Details for App #: Z142592
NO AHV RECORDS WERE FOUND FOR THIS BIN
Premises: 161 MANHATTAN AVENUE MANHATTAN BIN: 1055685     Block: 1843   Lot: 16
   

DOB NOW: Inspections

Application Completed and Certified

Filed: 161 MANHATTAN AV Census Tract:   193 Health Area:  2320
SIDEWALK SHED Admin Area:   Z - UPPER MANHATTAN Inspection Area:   C
NEW YORK, NY 10025 Community Board:   107
DOB Cross Street(s):   WEST 107 STREET,    WEST 108 STREET
Status:   C - JOB IS SIGNED OFF 03/29/2019
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  01/08/2014 10:00 AM
Application Entered:   01/08/2014 Job Start Date:   01/08/2014
Last Change:   03/29/2019 Job End Date:   01/08/2015
Appointment Status:   
Last Inspection By:   MARCIN DUBAJ       On     10/03/2018      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 010377 Licensee Name: MICHAEL BAPTISTE
Firm: 002413 Firm Name: WCK ELECTRIC CORP.
Firm Phone: 917-909-1048  Firm Address: 1274 PROSPECT AVENUE BROOKLYN NY 11218 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
W - SIDEWALK SHED WIRING & LIGHTING
Total Fee:  $40.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: KAMALJIT SINGH
Owner Business Name: BH&B CONSTRUCTION, INC
Authorized Representative:  MICHAEL BAPTISTE
Relationship To Owner:   SUB-CONTRACTOR


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
GND                   
Buildings Total                   
Total Units : 5 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  INSTALL LIGHT AND POWER FOR SIDEWALK SHED 75LF

 
Inspection Details
 

*NO AHV RECORDS WERE FOUND FOR THIS BIN
INSPECTION FOR APPLICATION #: Z142592
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 10/03/2018 10/03/2018 MJD C (15) (0) Y
INSPECTION COMMENTS: PASS, SHED REMOVED