5 Variance Information |
Is a residence within 200 feet of the site? |
Yes
|
No
|
|
Is all work being done within an enclosed building? |
Yes
|
No
|
|
Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
Does any of the work involve crane use? |
Yes
|
No
|
|
Total Days Requested: 10 |
Total Days Approved: 10 |
Approved for:
|
Start Day: |
Days: |
Hours From: |
Hours To: |
|
11/16/2022 |
Wednesday |
6:00 AM |
7:00 AM |
11/17/2022 |
Thursday |
6:00 AM |
7:00 AM |
11/18/2022 |
Friday |
6:00 AM |
7:00 AM |
11/21/2022 |
Monday |
6:00 AM |
7:00 AM |
11/22/2022 |
Tuesday |
6:00 AM |
7:00 AM |
11/23/2022 |
Wednesday |
6:00 AM |
7:00 AM |
11/24/2022 |
Thursday |
6:00 AM |
7:00 AM |
11/25/2022 |
Friday |
6:00 AM |
7:00 AM |
11/28/2022 |
Monday |
6:00 AM |
7:00 AM |
11/29/2022 |
Tuesday |
6:00 AM |
7:00 AM |
eRenew?
No |
|
Apply Reason: CONSTRUCTION ACTIVITIES WITH MINIMAL NOISE IMPACT |
Approved:
TRAFFIC CONGESTION (PEDESTRIAN AND/OR VEHICULAR) |
Description of Work: |
USE OF HOIST, DELIVERIES, CLEAN-UP AND HOUSEKEEPING, FA ADE INSTALLATION, BLOCK INSTALLATION, FRAMING AND DRYWALL INSTALLATION,CONCRETE PLACEMNET. CAULKING AND WATERPROOFING. DEBRIS CARTING. |