5 Variance Information |
Is a residence within 200 feet of the site? |
Yes
|
No
|
|
Is all work being done within an enclosed building? |
Yes
|
No
|
|
Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
Does any of the work involve crane use? |
Yes
|
No
|
|
Total Days Requested: 12 |
Total Days Approved: 6 |
Approved for:
|
Start Day: |
Days: |
Hours From: |
Hours To: |
|
08/28/2021 |
Saturday |
8:00 AM |
12:00 AM |
08/30/2021 |
Monday |
6:00 PM |
12:00 AM |
08/31/2021 |
Tuesday |
6:00 PM |
12:00 AM |
09/01/2021 |
Wednesday |
6:00 PM |
12:00 AM |
09/02/2021 |
Thursday |
6:00 PM |
12:00 AM |
09/03/2021 |
Friday |
6:00 PM |
12:00 AM |
eRenew?
Yes |
|
Apply Reason: CITY CONSTRUCTION PROJECT |
Approved:
SCHOOL ZONE |
eRenewal Authorized Day(s)/Time(s):
Monday 6:00 PM to 12:00 AM, Tuesday 6:00 PM to 12:00 AM, Wednesday 6:00 PM to 12:00 AM, Thursday 6:00 PM to 12:00 AM, Friday 6:00 PM to 12:00 AM, Saturday 8:00 AM to 12:00 AM |
Description of Work: |
GEN.CONSTR.REPLACEMENT OF EXISTING ELEVATOR/STAIR'B'BULKHEAD;REMOVAL OF OLD DUMBWATER SPACE;CONSTRUCTION OF NEW ELEVATOR MACHINE ROOM;VENTING OF EXISTING SHAFTS AT ROOF BULKHEAD AND ENLARGEMENT OF ELEVATOR DOOR OPENINGS AT EACH FLOOR LEVEL |