| 5 Variance Information |
| Is a residence within 200 feet of the site? |
Yes
|
No
|
|
| Is all work being done within an enclosed building? |
Yes
|
No
|
|
| Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
| Does any of the work involve crane use? |
Yes
|
No
|
|
| Total Days Requested: 5 |
| Total Days Approved: 5 |
|
Approved for:
|
| Start Day: |
Days: |
Hours From: |
Hours To: |
|
| 06/15/2020 |
Monday |
6:00 PM |
10:00 PM |
| 06/16/2020 |
Tuesday |
6:00 PM |
10:00 PM |
| 06/17/2020 |
Wednesday |
6:00 PM |
10:00 PM |
| 06/18/2020 |
Thursday |
6:00 PM |
10:00 PM |
| 06/19/2020 |
Friday |
6:00 PM |
10:00 PM |
| eRenew?
Yes |
|
| Apply Reason: PUBLIC SAFETY |
|
Approved:
EMERGENCY REPAIR WORK |
| eRenewal Authorized Day(s)/Time(s):
Monday 6:00 PM to 10:00 PM, Tuesday 6:00 PM to 10:00 PM, Wednesday 6:00 PM to 10:00 PM, Thursday 6:00 PM to 10:00 PM, Friday 6:00 PM to 10:00 PM |
| Description of Work: |
INTERIOR ABATEMENT ON 3RD FLOOR. OK to issue AHV with stipulation added to AHV description of work (Restrictions: No excessive noise after 10pm w/in 200' of residence.) |