| 5 Variance Information |
| Is a residence within 200 feet of the site? |
Yes
|
No
|
|
| Is all work being done within an enclosed building? |
Yes
|
No
|
|
| Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
| Does any of the work involve crane use? |
Yes
|
No
|
|
| Total Days Requested: 6 |
| Total Days Approved: 6 |
|
Approved for:
|
| Start Day: |
Days: |
Hours From: |
Hours To: |
|
| 03/02/2020 |
Monday |
10:01 PM |
2:00 AM |
| 03/03/2020 |
Tuesday |
10:01 PM |
2:00 AM |
| 03/04/2020 |
Wednesday |
10:01 PM |
2:00 AM |
| 03/05/2020 |
Thursday |
10:01 PM |
2:00 AM |
| 03/06/2020 |
Friday |
10:01 PM |
2:00 AM |
| eRenew?
No |
|
| Apply Reason: CONSTRUCTION ACTIVITIES WITH MINIMAL NOISE IMPACT |
|
Approved:
HAZARDOUS CONDITIONS |
| Description of Work: |
REMOVAL AND INSTALLATION OF INTERIOR NON-BEARING PARTITIONS, MODIFICATIONS TO EXISTING HVAC SYSTEM,INTERIOR DEMOLITION, SITE CLEAN UP. ALL WORK WILL TAKE PLACE ON THE 19TH&25TH FLOORS. ADDITIONAL TIME REQUIRED TO MAINTAIN SCHEDULE.NOTE: WITHIN ENCLOSED BUILDING ONLY |