5 Variance Information |
Is a residence within 200 feet of the site? |
Yes
|
No
|
|
Is all work being done within an enclosed building? |
Yes
|
No
|
|
Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
Does any of the work involve crane use? |
Yes
|
No
|
|
Total Days Requested: 14 |
Total Days Approved: 14 |
Approved for:
|
Start Day: |
Days: |
Hours From: |
Hours To: |
|
10/29/2019 |
Tuesday |
6:00 PM |
10:00 PM |
10/30/2019 |
Wednesday |
6:00 PM |
10:00 PM |
10/31/2019 |
Thursday |
6:00 PM |
10:00 PM |
11/01/2019 |
Friday |
6:00 PM |
10:00 PM |
11/02/2019 |
Saturday |
7:00 AM |
5:00 PM |
11/03/2019 |
Sunday |
9:00 AM |
5:00 PM |
11/04/2019 |
Monday |
6:00 PM |
10:00 PM |
11/05/2019 |
Tuesday |
6:00 PM |
10:00 PM |
11/06/2019 |
Wednesday |
6:00 PM |
10:00 PM |
11/07/2019 |
Thursday |
6:00 PM |
10:00 PM |
11/08/2019 |
Friday |
6:00 PM |
10:00 PM |
11/09/2019 |
Saturday |
7:00 AM |
5:00 PM |
11/10/2019 |
Sunday |
9:00 AM |
5:00 PM |
11/11/2019 |
Monday |
6:00 PM |
10:00 PM |
eRenew?
No |
|
Apply Reason: PUBLIC SAFETY |
Approved:
HAZARDOUS CONDITIONS |
Description of Work: |
SAT 7A-5P & SUN 9A-5P:FRAMING,DRYWALL,TAPE,TILE & STONE INSTALL,PAINT,MEP & FLOORING.WORK IS WITHIN ENCLOSED BLDG & WILL NOT GENERATE NOISE. MON-FRI 6P-10P & SAT 9A-5P: AS ABOVE PLUS DEBRIS REMOVAL,DELIVERIES & EXT. PANEL & ROOFING INSTALL. NOTE: SUBJEC TO PSWO |