5 Variance Information |
Is a residence within 200 feet of the site? |
Yes
|
No
|
|
Is all work being done within an enclosed building? |
Yes
|
No
|
|
Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
Does any of the work involve crane use? |
Yes
|
No
|
|
Total Days Requested: 10 |
Total Days Approved: 10 |
Approved for:
|
Start Day: |
Days: |
Hours From: |
Hours To: |
|
08/27/2019 |
Tuesday |
6:00 PM |
10:00 PM |
08/28/2019 |
Wednesday |
6:00 PM |
10:00 PM |
08/29/2019 |
Thursday |
6:00 PM |
10:00 PM |
08/30/2019 |
Friday |
6:00 PM |
10:00 PM |
08/31/2019 |
Saturday |
7:00 AM |
6:00 PM |
09/03/2019 |
Tuesday |
6:00 PM |
10:00 PM |
09/04/2019 |
Wednesday |
6:00 PM |
10:00 PM |
09/05/2019 |
Thursday |
6:00 PM |
10:00 PM |
09/06/2019 |
Friday |
6:00 PM |
10:00 PM |
09/07/2019 |
Saturday |
7:00 AM |
6:00 PM |
eRenew?
No |
|
Apply Reason: CONSTRUCTION ACTIVITIES WITH MINIMAL NOISE IMPACT |
Approved:
HAZARDOUS CONDITIONS |
Description of Work: |
FOUNDATION WORK FOR EXISTING BUILDING. THERE IS A CIVIL MAIN WATER WORK ON THE STREET IN DAYTIME. WORK IN AFTER HOURS IF NEEDED TO AVOID THE IMPACT TO THIS WORK AND THE CIVIL WORK. |