| 5 Variance Information |
| Is a residence within 200 feet of the site? |
Yes
|
No
|
|
| Is all work being done within an enclosed building? |
Yes
|
No
|
|
| Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
| Does any of the work involve crane use? |
Yes
|
No
|
|
| Total Days Requested: 14 |
| Total Days Approved: 14 |
|
Approved for:
|
| Start Day: |
Days: |
Hours From: |
Hours To: |
|
| 07/22/2019 |
Monday |
12:00 AM |
11:59 PM |
| 07/23/2019 |
Tuesday |
12:00 AM |
11:59 PM |
| 07/24/2019 |
Wednesday |
12:00 AM |
11:59 PM |
| 07/25/2019 |
Thursday |
12:00 AM |
11:59 PM |
| 07/26/2019 |
Friday |
12:00 AM |
11:59 PM |
| 07/27/2019 |
Saturday |
12:00 AM |
11:59 PM |
| 07/28/2019 |
Sunday |
12:00 AM |
11:59 PM |
| 07/29/2019 |
Monday |
12:00 AM |
11:59 PM |
| 07/30/2019 |
Tuesday |
12:00 AM |
11:59 PM |
| 07/31/2019 |
Wednesday |
12:00 AM |
11:59 PM |
| 08/01/2019 |
Thursday |
12:00 AM |
11:59 PM |
| 08/02/2019 |
Friday |
12:00 AM |
11:59 PM |
| 08/03/2019 |
Saturday |
12:00 AM |
11:59 PM |
| 08/04/2019 |
Sunday |
12:00 AM |
11:59 PM |
| eRenew?
No |
|
| Apply Reason: PUBLIC SAFETY |
|
Approved:
HAZARDOUS CONDITIONS |
| Description of Work: |
ADDRESS IS 553 WEST 30TH ST. ALL WORK ASSOCIATED WITH THE CONST OF A NEW BUILDING INCLUDING MECHANICAL, PIPING, ELEVATORS, HOIST, DELIVERY AND REMOVAL. GARBAGE PACKER USE TO START AT 6AM AS PER DEP NOISE MITIGATION PLAN. |