5 Variance Information |
Is a residence within 200 feet of the site? |
Yes
|
No
|
|
Is all work being done within an enclosed building? |
Yes
|
No
|
|
Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
Does any of the work involve crane use? |
Yes
|
No
|
|
Total Days Requested: 8 |
Total Days Approved: 7 |
Approved for:
|
Start Day: |
Days: |
Hours From: |
Hours To: |
|
06/22/2019 |
Saturday |
10:00 AM |
4:00 PM |
06/24/2019 |
Monday |
6:00 PM |
8:00 PM |
06/25/2019 |
Tuesday |
6:00 PM |
8:00 PM |
06/26/2019 |
Wednesday |
6:00 PM |
8:00 PM |
06/27/2019 |
Thursday |
6:00 PM |
8:00 PM |
06/28/2019 |
Friday |
6:00 PM |
8:00 PM |
06/29/2019 |
Saturday |
10:00 AM |
4:00 PM |
eRenew?
Yes |
|
Apply Reason: CONSTRUCTION ACTIVITIES WITH MINIMAL NOISE IMPACT |
Approved:
DEBRIS REMOVAL |
eRenewal Authorized Day(s)/Time(s):
Monday 6:00 PM to 8:00 PM, Tuesday 6:00 PM to 8:00 PM, Wednesday 6:00 PM to 8:00 PM, Thursday 6:00 PM to 8:00 PM, Friday 6:00 PM to 8:00 PM, Saturday 10:00 AM to 4:00 PM |
Description of Work: |
REMOVAL AND INSTALLATION OF INTERIOR NON LOAD BEARING PARTITIONS, AND INTERIOR MECHANICAL WORK INTERIOR STRUCTURAL WORK. DELIVERIES, SITE CLEAN UP, AND DEBRIS REMOVAL. NO PACKER USE AFTER 10 PM, OR BEFORE 9AM ON WEEKENDS |