| 5 Variance Information |
| Is a residence within 200 feet of the site? |
Yes
|
No
|
|
| Is all work being done within an enclosed building? |
Yes
|
No
|
|
| Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
| Does any of the work involve crane use? |
Yes
|
No
|
|
| Total Days Requested: 14 |
| Total Days Approved: 14 |
|
Approved for:
|
| Start Day: |
Days: |
Hours From: |
Hours To: |
|
| 01/28/2019 |
Monday |
6:00 PM |
10:00 PM |
| 01/29/2019 |
Tuesday |
6:00 PM |
10:00 PM |
| 01/30/2019 |
Wednesday |
6:00 PM |
10:00 PM |
| 01/31/2019 |
Thursday |
6:00 PM |
10:00 PM |
| 02/01/2019 |
Friday |
6:00 PM |
10:00 PM |
| 02/02/2019 |
Saturday |
9:00 AM |
5:00 PM |
| 02/03/2019 |
Sunday |
9:00 AM |
5:00 PM |
| 02/04/2019 |
Monday |
6:00 PM |
10:00 PM |
| 02/05/2019 |
Tuesday |
6:00 PM |
10:00 PM |
| 02/06/2019 |
Wednesday |
6:00 PM |
10:00 PM |
| 02/07/2019 |
Thursday |
6:00 PM |
10:00 PM |
| 02/08/2019 |
Friday |
6:00 PM |
10:00 PM |
| 02/09/2019 |
Saturday |
9:00 AM |
5:00 PM |
| 02/10/2019 |
Sunday |
9:00 AM |
5:00 PM |
| eRenew?
Yes |
|
| Apply Reason: PUBLIC SAFETY |
|
Approved:
HAZARDOUS CONDITIONS |
| eRenewal Authorized Day(s)/Time(s):
Monday 6:00 PM to 10:00 PM, Tuesday 6:00 PM to 10:00 PM, Wednesday 6:00 PM to 10:00 PM, Thursday 6:00 PM to 10:00 PM, Friday 6:00 PM to 10:00 PM, Saturday 9:00 AM to 5:00 PM, Sunday 9:00 AM to 5:00 PM |
| Description of Work: |
CONVERSION OF EXISTING COMMUNITY FACILITY TO RETAIL.INSTALL NEW MH DUCTWORK WITH A/C UNITS.STRUCTURAL WORK TO LOWER GROUND FLOOR&NEW ROOF FRAMING REDUCED TO EXISTING 4TH FL.GENERAL CONCRETE WORK ALONG WITH POURING OF CONCRETE.ELEVATOR WORK. |