| 5 Variance Information |
| Is a residence within 200 feet of the site? |
Yes
|
No
|
|
| Is all work being done within an enclosed building? |
Yes
|
No
|
|
| Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
| Does any of the work involve crane use? |
Yes
|
No
|
|
| Total Days Requested: 10 |
| Total Days Approved: 10 |
|
Approved for:
|
| Start Day: |
Days: |
Hours From: |
Hours To: |
|
| 09/24/2018 |
Monday |
6:00 PM |
11:00 PM |
| 09/25/2018 |
Tuesday |
6:00 PM |
11:00 PM |
| 09/26/2018 |
Wednesday |
6:00 PM |
11:00 PM |
| 09/27/2018 |
Thursday |
6:00 PM |
11:00 PM |
| 09/28/2018 |
Friday |
6:00 PM |
11:00 PM |
| 10/01/2018 |
Monday |
6:00 PM |
11:00 PM |
| 10/02/2018 |
Tuesday |
6:00 PM |
11:00 PM |
| 10/03/2018 |
Wednesday |
6:00 PM |
11:00 PM |
| 10/04/2018 |
Thursday |
6:00 PM |
11:00 PM |
| 10/05/2018 |
Friday |
6:00 PM |
11:00 PM |
| eRenew?
No |
|
| Apply Reason: PUBLIC SAFETY |
|
Approved:
DEBRIS REMOVAL |
| Description of Work: |
REMOVAL OF EXISTING MEZZANINE STRUCTURAL SLAB BETWEEN EXISTING BEAMS. THERE IS NO REMOVAL OR ALTERATION OF EXISTING STRUCTURAL FRAMING OR CONNECTIONS. THERE IS NO CHANGE TO LOAD PATH OR STAB |