| Total Days Requested: 14 |
| Total Days Approved: 14 |
|
Approved for:
|
| Start Day: |
Days: |
Hours From: |
Hours To: |
|
| 07/28/2016 |
Thursday |
6:00 AM |
11:00 PM |
| 07/29/2016 |
Friday |
6:00 AM |
11:00 PM |
| 07/30/2016 |
Saturday |
6:00 AM |
6:00 PM |
| 07/31/2016 |
Sunday |
6:00 AM |
6:00 PM |
| 08/01/2016 |
Monday |
6:00 AM |
11:00 PM |
| 08/02/2016 |
Tuesday |
6:00 AM |
11:00 PM |
| 08/03/2016 |
Wednesday |
6:00 AM |
11:00 PM |
| 08/04/2016 |
Thursday |
6:00 AM |
11:00 PM |
| 08/05/2016 |
Friday |
6:00 AM |
11:00 PM |
| 08/06/2016 |
Saturday |
6:00 AM |
6:00 PM |
| 08/07/2016 |
Sunday |
6:00 AM |
6:00 PM |
| 08/08/2016 |
Monday |
6:00 AM |
11:00 PM |
| 08/09/2016 |
Tuesday |
6:00 AM |
11:00 PM |
| 08/10/2016 |
Wednesday |
6:00 AM |
11:00 PM |
| eRenew?
Yes |
|
| Apply Reason: PUBLIC SAFETY |
|
Approved:
TRAFFIC CONGESTION (PEDESTRIAN AND/OR VEHICULAR) |
| eRenewal Authorized Day(s)/Time(s):
Monday 6:00 AM to 11:00 PM, Tuesday 6:00 AM to 11:00 PM, Wednesday 6:00 AM to 11:00 PM, Thursday 6:00 AM to 11:00 PM, Friday 6:00 AM to 11:00 PM, Saturday 6:00 AM to 6:00 PM, Sunday 6:00 AM to 6:00 PM |
| Description of Work: |
WEEKDAY & WEEKEND: OPERATION OF GENERATOR TO OPERATE SITE PUMPS. WEEKNIGHTS, 6PM TO 11PM AND SAT & SUN, 7AM TO 6PM: STEEL ERECTION WITH CRANE UNDER CN 334/16. SUPERSTRUCTURE WORK, CONCRETE WORK, PLACEMENT OF FORMWORK & REBAR, SITE UTILITY WORK, CON ED VAULT WORK ON UNMAPPED STREET, MEP WORK AND SITE CLEAN-UP. NOTE: NO CONCRETE PUMPING OR GARBAGE PACKERS USE BEFORE 7AM OR AFTER 10PM PER DBC. |