| 5 Variance Information |
| Is a residence within 200 feet of the site? |
Yes
|
No
|
|
| Is all work being done within an enclosed building? |
Yes
|
No
|
|
| Does any of the work involve full or partial demolition? |
Yes
|
No
|
|
| Does any of the work involve crane use? |
Yes
|
No
|
|
| Total Days Requested: 12 |
| Total Days Approved: 12 |
|
|
| Start Day: |
Days: |
Hours From: |
Hours To: |
|
| 11/24/2012 |
Saturday |
9:00 AM |
6:00 PM |
| 11/26/2012 |
Monday |
6:00 AM |
8:00 PM |
| 11/27/2012 |
Tuesday |
6:00 AM |
8:00 PM |
| 11/28/2012 |
Wednesday |
6:00 AM |
8:00 PM |
| 11/29/2012 |
Thursday |
6:00 AM |
8:00 PM |
| 11/30/2012 |
Friday |
6:00 AM |
8:00 PM |
| 12/01/2012 |
Saturday |
9:00 AM |
6:00 PM |
| 12/03/2012 |
Monday |
6:00 AM |
8:00 PM |
| 12/04/2012 |
Tuesday |
6:00 AM |
8:00 PM |
| 12/05/2012 |
Wednesday |
6:00 AM |
8:00 PM |
| 12/06/2012 |
Thursday |
6:00 AM |
8:00 PM |
| 12/07/2012 |
Friday |
6:00 AM |
8:00 PM |
| eRenew?
No |
|
| Apply Reason: PUBLIC SAFETY |
|
Approved:
TRAFFIC CONGESTION (PEDESTRIAN AND/OR VEHICULAR) |
| Description of Work: |
WEEKDAYS - DELIVERY OF MATERIALS TO JOB SITE. CONCRETE FINISHING WORK FROM 6PM THRU 8PM. NO CONSTRUCTION WORK WILL TAKE PLACE WEEKDAY MORNINGS. SATURDAYS -BACKFILL AND FOUNDATION WORK AT OSP. DELIVERY OF MATERIALS TO JOBSITE. LIFTING MATERIALS WITH CRANE UNDER CN# 685/11. SUPERSTRUCTURE CONCRETE FORMWORK AND REBAR & MEP LAYOUT AND SLEEVES AT CELLAR THRU 20TH FLOOR. CONCRETE POURS/PLACEMENT FROM CELLAR THRU 20TH FLOOR. JUMPING HOIST FROM 1ST TO 20TH FLOOR. INSTALLATION OF STANDPIPE FROM CELLAR THRU 20TH FLOOR. MASONRY WORK FROM 1ST THRU 20TH FLOORS. <<M-F: 6AM-8PM /SAT: 9AM-6PM PER BC >> |