Total Days Requested: 7 |
Total Days Approved: 7 |
|
Start Day: |
Days: |
Hours From: |
Hours To: |
|
09/17/2012 |
Monday |
12:01 AM |
11:59 PM |
09/18/2012 |
Tuesday |
12:01 AM |
11:59 PM |
09/19/2012 |
Wednesday |
12:01 AM |
11:59 PM |
09/20/2012 |
Thursday |
12:01 AM |
11:59 PM |
09/21/2012 |
Friday |
12:01 AM |
11:59 PM |
09/22/2012 |
Saturday |
12:01 AM |
11:59 PM |
09/23/2012 |
Sunday |
12:01 AM |
11:59 PM |
eRenew?
Yes |
|
Apply Reason: PUBLIC SAFETY |
Approved:
TRAFFIC CONGESTION (PEDESTRIAN AND/OR VEHICULAR) |
eRenewal Authorized Day(s)/Time(s):
Monday 12:01 AM to 11:59 PM, Tuesday 12:01 AM to 11:59 PM, Wednesday 12:01 AM to 11:59 PM, Thursday 12:01 AM to 11:59 PM, Friday 12:01 AM to 11:59 PM, Saturday 12:01 AM to 11:59 PM, Sunday 12:01 AM to 11:59 PM |
Description of Work: |
ATLANTIC YARDS - ROOFING, REINFORCINGFORMWORK, FO CONCRETE, CRANE MAINTENANCE, INT. CONSTRUCTION, MASONRY, MECH., PLUMBING AND ELECTRICAL, DELIVERIES, CURTAINWALL & FACADE INSTALLATION, SITEWORK & SITE UTILITIES,TRENCH EXCAVATION AND BACKFILL. , FOOD SERVICE EQUIPMENT INSTALLATION, FIRE SPRINKLER PIPING #320152455, BOWL EPOXY COATING, BOWL RAILINGS. SEATING. RETRACTABLE SEATING INSTALLATION, SCOREBOARD AND VIDEOBOARD INSTALLATION, SIGNAGE INSTALLATION AND ACOUSTICAL TREATMENTS AT SEATING BOWL. ELEVATOR AND ESCALATOR MAINTENANCE, SPORT EQUIPMENT INSTALLATION, BOWL PLATOFRM INSTALLATION. |