Disposition |
Disposition |
Inspection |
Date |
|
Date |
Code |
By |
|
| 7 |
01/08/2014 |
L2 |
STOP WORK ORDER FULLY RESCINDED |
2569 |
12/18/2013 |
| |
|
|
FULL LIFT OF SWO |
|
| 6 |
12/11/2013 |
L3 |
STOP WORK ORDER PARTIALLY RESCINDED |
9NCX |
12/11/2013 |
| |
|
|
SWO MODIFIED TO ALLOW CONCRETE TO GRADE LEVEL AND ALL STEEL WORK TO ROOF LEVEL WITH MONITORING DAILY DOB PE EXID |
|
| 5 |
11/08/2013 |
L3 |
STOP WORK ORDER PARTIALLY RESCINDED |
9NCX |
11/08/2013 |
| |
|
|
OK TO COMPLETE CONCRETING IN BASEMENT TO STREET LEVEL/ COMPLETE PILES/OKTO COMPLETE REBAR UP TO STREET LEVEL |
|
| 4 |
10/24/2013 |
L3 |
STOP WORK ORDER PARTIALLY RESCINDED |
9NCX |
10/23/2013 |
| |
|
|
OK TO COMPLETE COMPLETE REMAINING PILES AS PER SUBMITTED LAYOUT PLAN EX/ID |
|
| 3 |
10/23/2013 |
L3 |
STOP WORK ORDER PARTIALLY RESCINDED |
9NCX |
10/23/2013 |
| |
|
|
OK TO COMPLETE FORMS AND REBAR IN BASEMENT AREA / ALLOW SITE SURVEY WORK FOR THE PILES ONLY |
|
| 2 |
10/21/2013 |
A3 |
FULL STOP WORK ORDER SERVED |
2240 |
10/21/2013 |
| |
|
|
NO ENGINEER ON SITE MONITORING THE STRUCTURAL PILE INSTALL CHIEF ENGINEER ON SITE OBTAINED CONDITIONS ADJ PROP |
|
| 1 |
10/21/2013 |
E8 |
COMPLAINT ASSIGNED TO EXCAVATION INSPECTION & AUDITS TEAM |
2270 |
10/21/2013 |
| |
|
|
REFER TO EXCAVATIONS UNIT. EXCAVATIONS UNIT ISSUED PARTIAL S TOP WORK ORDER |
|