FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
04/22/2019 |
122888349 |
06 |
A1 |
P APPROVED |
04/23/2019 |
|
LIPSON |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003
|
03/13/2018 |
122888349 |
05 |
A1 |
P APPROVED |
03/16/2018 |
|
LIPSON |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
09/25/2017 |
121288604 |
03 |
A2 |
P APPROVED |
10/06/2017 |
|
SHARMA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
09/25/2017 |
123070390 |
02 |
A2 |
P APPROVED |
09/26/2017 |
|
SHARMA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
06/30/2017 |
121288604 |
02 |
A2 |
G PAA FEE DUE |
06/30/2017 |
|
SHARMA |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 07/26/2017
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
06/19/2017 |
121229429 |
02 |
A2 |
X SIGNED OFF |
10/19/2017 |
0074781 PE |
RENFROE |
|
NOT APPLICABLE
|
|
STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
06/19/2017 |
121229429 |
01 |
A2 |
X SIGNED OFF |
10/19/2017 |
0026066 RA |
REGAN |
|
NOT APPLICABLE
|
|
DEMOLISH AND CONSTRUCT INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
05/22/2017 |
121288604 |
01 |
A2 |
X SIGNED OFF |
06/15/2018 |
0082331 PE |
SHARMA |
|
NOT APPLICABLE
|
|
INSTALL NEW MECHANICAL DUCTWORK ALONG WITH A/C UNITS. INSTALL NEW PLUMBING
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
05/08/2017 |
122684700 |
03 |
A2 |
P APPROVED |
05/09/2017 |
|
SHARMA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
04/26/2017 |
122684700 |
02 |
A2 |
P APPROVED |
05/01/2017 |
|
SHARMA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
04/17/2017 |
122888349 |
04 |
A1 |
P APPROVED |
04/18/2017 |
0085879 PE |
QUINTANI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
04/07/2017 |
123072888 |
01 |
A2 |
X SIGNED OFF |
09/04/2018 |
0082331 PE |
SHARMA |
|
NOT APPLICABLE
|
|
MANUAL & AUTOMATIC SMOKE/HEAT DETECTION/SPRINKLER ALARM SYSTEM AS SHOWN ON
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
04/07/2017 |
123070390 |
01 |
A2 |
X SIGNED OFF |
11/01/2017 |
0082331 PE |
SHARMA |
|
NOT APPLICABLE
|
|
INSTALL NEW SPRINKLER HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS FILED
|
|
Work on Floor(s): CEL,ROF 001 thru 003
|
11/30/2016 |
122948926 |
01 |
A2 |
X SIGNED OFF |
06/01/2017 |
0022234 RA |
LIPSON |
|
NOT APPLICABLE
|
|
WINDOW REPLACEMENTS, STOREFRONT WORK, FACADE/BRICK MASONRY WORK. FENCE FI
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
11/04/2016 |
122913026 |
01 |
A2 |
X SIGNED OFF |
11/29/2016 |
0022234 RA |
LIPSON |
|
NOT APPLICABLE
|
|
MOCK UP STRUCTURE AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, E
|
|
Work on Floor(s): ROF
|
10/11/2016 |
122888349 |
03 |
A1 |
X SIGNED OFF |
04/26/2019 |
0069888 PE |
OPPENHEI |
|
NOT APPLICABLE
|
|
STRUCTURAL WORK AS SHOWN ON DRAWINGS FILED HEREWITH.
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
10/11/2016 |
122888349 |
02 |
A1 |
X SIGNED OFF |
04/26/2019 |
0085879 PE |
QUINTANI |
|
NOT APPLICABLE
|
|
INSTALL NEW MECHANICAL DUCTWORK AND UNITS . REMOVE AND INSTALL NEW PLUMBIN
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
10/11/2016 |
122888349 |
01 |
A1 |
X SIGNED OFF |
04/26/2019 |
0022234 RA |
LIPSON |
|
NOT APPLICABLE
|
|
FILING HEREWITH CHANGE OF USE FROM STORAGE/FACTORY TO RETAIL.ALSO DEMOLISH
|
|
Work on Floor(s): CEL,001,002,003
|
08/11/2016 |
122684700 |
01 |
A2 |
X SIGNED OFF |
05/24/2017 |
0082331 PE |
SHARMA |
|
NOT APPLICABLE
|
|
INSTALL NEW TEMPORARY LOOP HEADS AND RELATED PIPING AS SHOWN ON DRAWINGS F
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
08/11/2016 |
122846493 |
02 |
A2 |
X SIGNED OFF |
06/02/2017 |
0082331 PE |
SHARMA |
|
NOT APPLICABLE
|
|
REMOVAL OF PERIMETER RADIATORS. REMOVE PLUMBING FIXTURES AND RELATED PIPIN
|
|
Work on Floor(s): 001,002,003
|
08/11/2016 |
122846493 |
01 |
A2 |
X SIGNED OFF |
06/02/2017 |
0022234 RA |
LIPSON |
|
NOT APPLICABLE
|
|
DEMOLISH INTERIOR PARTITIONS, CEILINGS AND DOORS AS SHOWN ON DRAWINGS FILE
|
|
Work on Floor(s): 001,002,003
|
08/11/2016 |
122846466 |
01 |
A2 |
R PERMIT-ENTIRE |
05/05/2017 |
0082331 PE |
SHARMA |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/17/2017 REMOVE BOILER. REMOVAL OF 2 275 GALLON TANKS AS S
|
|
Work on Floor(s): CEL
|
07/29/2016 |
122837779 |
02 |
A2 |
X SIGNED OFF |
06/09/2017 |
0069888 PE |
OPPENHEI |
|
NOT APPLICABLE
|
|
STRUCTURAL EMERGENCY REPAIRS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANG
|
|
Work on Floor(s): 001,002,003,ROF
|
07/29/2016 |
122837779 |
01 |
A2 |
X SIGNED OFF |
06/09/2017 |
0084628 PE |
ALLEN |
|
NOT APPLICABLE
|
|
MINOR REPAIRS AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRES
|
|
Work on Floor(s): 001,002,003,ROF
|
06/20/2016 |
140511435 |
01 |
A3 |
X SIGNED OFF |
06/06/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): OSP
|
06/20/2016 |
140511499 |
01 |
A3 |
X SIGNED OFF |
06/06/2017 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN USE,
|
|
Work on Floor(s): OSP
|
07/26/2013 |
121712272 |
01 |
A3 |
X SIGNED OFF |
08/31/2017 |
0089587 PE |
PHAGOO |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS
|
|
Work on Floor(s): OSP
|
06/07/2011 |
120718679 |
01 |
A3 |
X SIGNED OFF |
09/20/2013 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION OF A TEMPORARY SAFETY DEBRIS NETTING AS A TEMPORARY REPLACEME
|
|
Work on Floor(s): OSP
|
03/01/2011 |
120601679 |
01 |
A3 |
X SIGNED OFF |
08/31/2017 |
0029017 RA |
WESOLOWS |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS
|
|
Work on Floor(s): OSP
|
03/30/2007 |
104695849 |
01 |
A3 |
X SIGNED OFF |
07/18/2017 |
OT |
LARSEN |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED 142' DURING FACADE REPAIR. NO C
|
|
Work on Floor(s): 001
|
02/21/2007 |
104682318 |
01 |
A3 |
X SIGNED OFF |
04/20/2007 |
OT |
LARSEN |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALKSHED 12' DURING FACADE REPAIR.NO CHANG
|
|
Work on Floor(s): 001
|
01/22/2007 |
104657774 |
01 |
A2 |
X SIGNED OFF |
07/07/2017 |
0016155 RA |
Waugh |
|
NOT APPLICABLE
|
|
Facade repair and replacing existing roof stair bulkhead. No change, to us
|
|
Work on Floor(s): ROF 001 thru 003
|
10/01/1991 |
100314296 |
01 |
A3 |
X SIGNED OFF |
07/18/2017 |
|
JACONSON |
|
NOT APPLICABLE
|
|
INSTALLATION OF SIDEWALK BRIDGE 135' ON LAFAYETTE ST. HEAVY DUTY NO CHAN
|
|
Work on Floor(s): GRO,UND
|
07/29/1991 |
100283097 |
01 |
A2 |
X SIGNED OFF |
11/20/1991 |
0053953 PE |
SEUNG |
|
NOT APPLICABLE
|
|
TO INSTALL NEW STORE FRONT IN EXISTING STORE, NO CHANGE IN EGRESS, USE
|
|
Work on Floor(s): 1
|