FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
09/08/2020 |
420652877 |
11 |
NB |
P APPROVED |
09/11/2020 |
|
HILL |
|
AMENDED 03/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2,PT3 001 thru 045
|
06/27/2019 |
421246459 |
04 |
A3 |
P APPROVED |
07/08/2019 |
|
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
06/27/2019 |
421246930 |
04 |
A3 |
P APPROVED |
07/08/2019 |
|
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
11/19/2018 |
440404180 |
02 |
A2 |
P APPROVED |
11/29/2018 |
|
MCCOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
06/15/2018 |
421644536 |
02 |
A2 |
X SIGNED OFF |
10/17/2019 |
0081085 PE |
PARGANOS |
|
NOT APPLICABLE
|
|
SUBSEQUENT FILING FOR PLUMBING, SPRINKLER AND MECHANICAL WORKS.
|
|
Work on Floor(s): 001
|
06/15/2018 |
421644536 |
01 |
A2 |
X SIGNED OFF |
10/17/2019 |
0022132 RA |
CHAN |
|
NOT APPLICABLE
|
|
INTERIOR BUILD OUT FOR RETAIL SPACE NO.1 (COFFEE SHOP)ON FIRSTFLOOR.
|
|
Work on Floor(s): 001
|
04/12/2018 |
421622042 |
01 |
A2 |
X SIGNED OFF |
05/16/2019 |
0065403 PE |
GERMAIN |
|
NOT APPLICABLE
|
|
INSTALL (1) NEW GAS FIRED SIDE WALL DIRECT VEWNT FIREPLACE WITH (1) NEW IN
|
|
Work on Floor(s): 1ST
|
11/20/2017 |
420652877 |
10 |
NB |
P APPROVED |
11/22/2017 |
0072039 PE |
DELPOZZO |
|
AMENDED 03/18/2016
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2,PT3 001 thru 045
|
10/16/2017 |
440442399 |
01 |
A3 |
X SIGNED OFF |
02/11/2019 |
0028264 RA |
HILL |
|
NOT APPLICABLE
|
|
INSTALLATION OF MARQUEE IN CONJUNCTION WITH NEW BUILDING APPLICATION #:
|
|
Work on Floor(s): OSP
|
10/04/2017 |
421561456 |
01 |
A2 |
X SIGNED OFF |
07/26/2019 |
0020635 RA |
SCHMERZL |
|
NOT APPLICABLE
|
|
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT IN CONJUNCTION WITH N
|
|
Work on Floor(s): 1ST,MEZ,21S
|
09/28/2017 |
440213038 |
02 |
A2 |
P APPROVED |
10/05/2017 |
|
DELPOZZO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2 001 thru 045
|
09/26/2017 |
440213010 |
04 |
A2 |
P APPROVED |
10/05/2017 |
|
DELPOZZO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2 001 thru 045
|
09/07/2017 |
440432783 |
01 |
A2 |
X SIGNED OFF |
08/23/2019 |
0020635 RA |
SCHMERZL |
|
NOT APPLICABLE
|
|
FILING TENANT PROTECTION PLAN IN CONJUNCTION WITH NEW BUILDING 420652877
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2 001 thru 045
|
08/09/2017 |
440425700 |
01 |
A3 |
X SIGNED OFF |
03/30/2019 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
INSTALLATION OF SCAFFOLD AS PER PLANS FILED HEREWITH. FILED IN CONJUNCTION
|
|
Work on Floor(s): 045
|
07/27/2017 |
440422437 |
01 |
A2 |
X SIGNED OFF |
03/09/2019 |
0072039 PE |
DELPOZZO |
|
NOT APPLICABLE
|
|
INSTALLATION OF GAS BOILERS ASSOCIATED WITH NEW BUILDING. FILED IN CONJUNC
|
|
Work on Floor(s): 045
|
07/17/2017 |
440213010 |
03 |
A2 |
P APPROVED |
08/01/2017 |
|
DELPOZZO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2 001 thru 045
|
05/30/2017 |
440404180 |
01 |
A2 |
X SIGNED OFF |
04/23/2019 |
0064477 PE |
MCCOY |
|
NOT APPLICABLE
|
|
INSTALLATION OF AREA DRAINS AT COURTYARD AS PER PLANS FILED HEREWITH. FILE
|
|
Work on Floor(s): OSP
|
04/28/2017 |
440399061 |
01 |
A3 |
X SIGNED OFF |
08/26/2019 |
0028264 RA |
HILL |
|
NOT APPLICABLE
|
|
FIRE PROTECTION PLAN FILED IN CONJUNCTION WITH NEW BUILDING APPLICATION #:
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2,PT3 001 thru 045
|
04/18/2017 |
420652877 |
09 |
NB |
P APPROVED |
10/05/2017 |
0072039 PE |
DELPOZZO |
|
AMENDED 03/18/2016
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2,PT3 001 thru 045
|
04/12/2017 |
420652877 |
08 |
NB |
P APPROVED |
11/16/2017 |
0028264 RA |
HILL |
|
AMENDED 03/18/2016
|
|
POST APPROVAL AMENDMENT FOR 01 NONE
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2,PT3 001 thru 045
|
03/08/2017 |
440389367 |
01 |
A2 |
X SIGNED OFF |
06/04/2019 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION OF MONORAIL SYSTEM AS PER PLAN FILED HEREWITH. NO CHANGE IN U
|
|
Work on Floor(s): ROF
|
03/02/2017 |
440388162 |
01 |
A2 |
X SIGNED OFF |
06/04/2019 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION OF MINI PICKER AS PER PLAN FILED HEREWITH. NO CHANGE IN USE,
|
|
Work on Floor(s): ROF
|
02/23/2017 |
440386896 |
01 |
A3 |
P APPROVED |
02/23/2017 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 05/08/2019 INSTALLATION OF MINI PICKER AS PER PLAN FILED HER
|
|
Work on Floor(s): ROF
|
02/08/2017 |
440382989 |
01 |
A3 |
H P/E IN PROCESS |
02/08/2017 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/08/2017 INSTALLATION OF MONORAIL SYSTEM AS PER PLAN FILED
|
|
Work on Floor(s): ROF
|
12/14/2016 |
421409121 |
01 |
A3 |
X SIGNED OFF |
09/24/2018 |
0086757 PE |
PERDEK |
|
NOT APPLICABLE
|
|
INSTALLATION OF OVERHEAD PROTECTION SYSTEM AS PER DRAWINGS DURING NEW BUIL
|
|
Work on Floor(s): OSP
|
12/07/2016 |
440213010 |
02 |
A2 |
P APPROVED |
12/30/2016 |
|
DELPOZZO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,MEZ,PT1,PT2 001 thru 045
|
10/14/2016 |
421246930 |
03 |
A3 |
P APPROVED |
10/14/2016 |
|
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
10/14/2016 |
421246459 |
03 |
A3 |
P APPROVED |
10/14/2016 |
|
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
10/07/2016 |
440350978 |
01 |
A2 |
X SIGNED OFF |
06/11/2018 |
0079415 PE |
DIALBERT |
|
NOT APPLICABLE
|
|
INSTALLATION OF AN ADT ACCESS SYSTEM ON THE ROOF AS PER PLANS. NO CHANGE I
|
|
Work on Floor(s): ROF
|
09/30/2016 |
440349339 |
01 |
A3 |
X SIGNED OFF |
10/10/2017 |
0032813 PE |
PARMET |
|
NOT APPLICABLE
|
|
INSTALLATION OF DEBRIS SHUTE AS SHOWN ON DRAWING. THERE WILL BE NO CHANGE
|
|
Work on Floor(s): ISP
|
09/29/2016 |
421246930 |
02 |
A3 |
P APPROVED |
10/03/2016 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
09/29/2016 |
421246459 |
02 |
A3 |
P APPROVED |
10/03/2016 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
05/23/2016 |
440313260 |
01 |
A2 |
D A/P ENTIRE |
05/23/2016 |
0029249 RA |
NICOLAZZ |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 07/22/2016 FILING FOR TEMP EGRESS PLAN
|
|
Work on Floor(s): 001
|
05/20/2016 |
440312831 |
01 |
A2 |
X SIGNED OFF |
09/06/2017 |
0029249 RA |
NICOLAZZ |
|
NOT APPLICABLE
|
|
FILING FOR TEMP EGRESS PLAN
|
|
Work on Floor(s): 001
|
04/27/2016 |
421246949 |
02 |
A3 |
P APPROVED |
04/28/2016 |
|
CASSALIA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF 137 LINEAR FEET OF HEAVY DU
|
|
Work on Floor(s): OSP
|
04/07/2016 |
440302183 |
01 |
A3 |
X SIGNED OFF |
04/15/2019 |
0077599 PE |
CUOCO |
|
NOT APPLICABLE
|
|
TEMPORARY INSTALLATION AND USE OF A JEKKO MPK20, JEKKO SPD 360 AND A BLUE
|
|
Work on Floor(s): 001 thru 045
|
02/25/2016 |
421269567 |
01 |
A2 |
X SIGNED OFF |
07/12/2019 |
0090583 PE |
LAMPARD |
|
NOT APPLICABLE
|
|
FILING FOR PERI COCOON PROTECTION SYSTEM FOR FLOORS 006-044
|
|
Work on Floor(s): 006 thru 044
|
02/03/2016 |
421251273 |
01 |
A3 |
X SIGNED OFF |
03/18/2019 |
0094852 PE |
CASSALIA |
|
NOT APPLICABLE
|
|
INSTALLATION OF ROOF PROTECTION OVER MTA SUB STATION AS PER DRAWINGS DURIN
|
|
Work on Floor(s): OSP
|
01/19/2016 |
421246949 |
01 |
A3 |
X SIGNED OFF |
03/18/2019 |
0094852 PE |
CASSALIA |
|
NOT APPLICABLE
|
|
INSTALLATION OF 137 LINEAR FEET OF HEAVY DUTY SIDEWALK SHED DURING NB CONS
|
|
Work on Floor(s): OSP
|
01/19/2016 |
421246930 |
01 |
A3 |
X SIGNED OFF |
07/09/2019 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
EAST HOIST - INSTALLATION OF A DUAL 7000 LBS CAPACITY PERSONNEL/MATERIAL H
|
|
Work on Floor(s): OSP
|